Breakspear Road South Extended work

HS2 Works notification: Update: Notice of works at Breakspear Road South, 9 – 14 May 2021

We wrote to you previously to advise you that we would be carrying out works from 7 to 9 May 2021. We need to extend the lane closure from 9 to 14 May 2021, in order to complete these works.

The road crossing at Breakspear Road South will become operational for our site traffic from 10 May 2021. The London Borough of Hillingdon has approved a speed limit reduction from 40mph to 30mph between Swakeleys Road and Breakspear Road, and to 20mph near the haul road crossing.

To ensure that this area is ready, we will be carrying out road and utility works along Breakspear Road South from 7 May 2021, in the area shown on the link below

These works will include the installation of concrete traffic barriers and line markings. Additionally, we will investigate the condition of the culvert system using a CCTV camera mounted on a small robot. Your utility services will not be affected.

Most of the work activities on the carriageways will be restricted to lane closures. However, for safety reasons there will be a full road closure needed for one night on 7 May.