HS2 works at Harvil Road and Breakspear Road South, 21 June to 31 July

From HS2

We wrote you in April to advise you that we would be carrying out bored piling works at Breakspear Road South to facilitate the construction of overbridges at these locations. From Monday 21st of June, we will start the next phase of these works which will continue until the end of July.

We do not expect there to be any noise and vibration or disturbance to nearby residents. Monitoring will be in place throughout these works.

Breakspear Road South closure

from HS2

We have been informed that the London Borough of Hillingdon will have a full road closure at Breakspear Road South on Monday 14 June 2021, for one week to carry out resurfacing works from the south of the Chiltern Line bridge to Swakeleys junction.

As a result of these works, the SCS site team at Breakspear Road South have cancelled their works planned for next week. (Notice of works for the U46 footpath road crossing HS2-EW-SCS-Ph1-Ar-So-S1-Traf-33-14/06/2021)

Newyears Green Lane & West Ruislip works

from HS2

Newyears Green Lane
We wrote to you recently to advise you that we would be carrying out ecological surveys on 17 May and 1 June along Newyears Green Lane. Due to poor weather conditions, we were unable to complete the surveys. We therefore require additional time to complete these works, which will now be completed on 1 and 14 June 2021. A road closure will be required between 8pm and 5am to ensure these works can be carried out safely.

West Ruislip
We will be carrying out works over one weekend (19 & 20 June 2021) in the bell mouth where vehicles access the site from Ickenham High Road. We are connecting a foul sewer from site to a chamber that sits underneath the centre of the junction.

Once connected the trench will be backfilled and the work area reinstated. We will carry out the main cut into the concrete within normal working hours on the Friday 18 June, to minimise noise on the weekend

Duration of works
The weekend of 19 and 20 June 2021
From 8am to 6pm

What to expect
An excavator and dumper trucks will be required to create the trench for the sewer

What we will do
Maintain access along the footpath and carriageway of Ickenham High Road

Breakspear Road South restrictions from LBH

From LBH

LONDON BOROUGH OF HILLINGDON TEMPORARY RESTRICTION OF TRAFFIC (BREAKSPEAR ROAD SOUTH, ICKENHAM) ORDER 2021 ROAD TRAFFIC REGULATION ACT 1984 SECTION 14(1)

1. Hillingdon Council gives notice that to enable repair works to be carried out by O’Hara Bros and to prevent the likelihood of danger to the public it made this Order, which will temporarily close Breakspear Road South, Ickenham from Swakeleys Road to outside Breakspear Road.

2. Diversion route will be in place via Breakspear Road, Bury Street, High Street, Ickenham Road, High Road, Swakeleys Road and vice versa. Nothing in the Order shall apply to prevent vehicular access to premises on or adjacent to the prohibited length of road insofar as access is reasonably practicable without interference with the said works.

3. The temporary restriction will be in operation between 08:00hrs on the 15 th June 2021 to 17:00hrs, on the 20th June 2021 and to such extent as indicated by traffic signs prescribed by the Traffic Signs Regulations and General Directions 2002. Road users should assume that the closure has been put into effect only if traffic signs have been erected stating that the road has been closed and the diversion route, if necessary is in place.

4. The Order, which is proposed will come into operation on 15 th June 2021, will continue in force for eighteen months or until work to which it relates is completed. However it is anticipated that the works will be completed within 5 Days.

Dated this 18 day of May 2021 Perry Scott Corporate Director of Infrastructure, Building Services & Transport

Harvil Road lane closures 17 May to 30 September: Update

FROM HS2

Update:

We wrote to you in April to advise that we would be carrying out utility works from 17 May to 30 September 2021 and over two weekends. However, additional weekend working will be required.

From 17 May 2021, we will be carrying out utility surveys and utility connection along Harvil Road as part of the road realignment works. Temporary traffic management and lane closures will be required to ensure these works can be carried out safely.

We hope to reduce the duration of the lane closure by working additional weekends.

Breakspear Road South Extended work

HS2 Works notification: Update: Notice of works at Breakspear Road South, 9 – 14 May 2021

We wrote to you previously to advise you that we would be carrying out works from 7 to 9 May 2021. We need to extend the lane closure from 9 to 14 May 2021, in order to complete these works.

The road crossing at Breakspear Road South will become operational for our site traffic from 10 May 2021. The London Borough of Hillingdon has approved a speed limit reduction from 40mph to 30mph between Swakeleys Road and Breakspear Road, and to 20mph near the haul road crossing.

To ensure that this area is ready, we will be carrying out road and utility works along Breakspear Road South from 7 May 2021, in the area shown on the link below

These works will include the installation of concrete traffic barriers and line markings. Additionally, we will investigate the condition of the culvert system using a CCTV camera mounted on a small robot. Your utility services will not be affected.

Most of the work activities on the carriageways will be restricted to lane closures. However, for safety reasons there will be a full road closure needed for one night on 7 May.

Newyears Green Lane 17 May and June 1

From HS2

HS2 Notice of works at Newyears Green Lane

On 17 May and 1 June 2021, we will be carrying out ecological surveys along Newyears Green Lane.


A road closure is required between 8pm and 5am to ensure these works can be carried out safely.

Duration of works
17 May and 1 June 2021 between 8pm and 5am
We may be on site for an hour before the start and/or end of each shift

What to expect
Temporary traffic management
Ecologists and surveying equipment

What we will do
Maintain access to your property at all times

Harvil Road lane closures 17 May to 30 September

FROM HS2

From 17 May we will be carrying out utility surveys and utility connection along Harvil Road as part of the road realignment works. Temporary traffic management and lane closures will be required to ensure the works can be carried out safely. We will work during off peak hours and out of hours where possible to minimise disruption. We do not expect your service to be interrupted however the utility company concerned will provide pre-notification to affected households if an interruption becomes necessary

Duration of works
From 17 May to 30 September 2021 between 8am and 6pm and Saturday 8am to 1pm. Extended hours on 22, 23, 29 and 30 May between 1pm to 6pm Saturday and 8am to 1pm Sunday

What to expect
Traffic management, operatives, and barrier equipment will be in place. Lane closures will be controlled by automatic signals supported by operatives during the busiest parts of the day


What we will do
Maintain access to your property at all times

More info’:
https://www.hs2.org.uk/work-items/notice-of-lane-closure-at-harvil-road-2/

From HS2

Notice of lane closure on Harvil Road

Ground investigation and CCTV survey
We wrote to you previously to advise you that we would be carrying out utility works from 19 to 30 April 2021. However, we have rearranged these dates and the works will now take place from 26 to 30 April 2021. We will undertake ground investigation and survey of the drainage system on Harvil Road from the junction of Skip Lane, down to our southernmost gates. For safety reasons, we will need to close a lane.

Duration of works
From 26 to 30 April between 8am and 5pm
We may be on site for an hour before the start and/or end of each shift

What to expect
Traffic management, operatives, excavation equipment to take samples and measurements, and surveying equipment, (including a CCTV camera) Lane closures controlled by automatic signals supported by operatives during the busiest parts of the day

What we will do
Maintain access to your property at all times