A40 utility works update

from HS2
What we are doing

Utility works on the A40 Western Avenue
We wrote to you in April about works on the A40 Western Avenue planned between 6 May and 30 September 2024. Due to ongoing works on the road network in Ealing, the start date for the works on the A40 Western Avenue has changed.

We are now planning to start our works on the A40 Western Avenue from 27 May until late-October 2024. The works will be located between Alperton Lane and Hanger Lane Gyratory.

On 20, 21 and 22 May from 10pm to 5am, an overnight lane closure will be in place on the A40 Western Avenue to install cameras.

Temporary changes to A40 tunnels
We will need to close the A40 tunnels overnight while the contraflow system is introduced, for safety reasons. This is during the first phase of the works. The tunnels will be closed overnight from 10pm to 6am with all traffic diverted via Hanger Lane Gyratory. You can view details about traffic management planned during each phase of the works via the link to the presentation in the link below.

We are not planning to close the tunnels during the remainder of the works. If there are any changes to our planned traffic management, we will provide updates via the HS2 in your area map.

We will continue working with utility providers, Transport for London and Ealing Council to coordinate works on the local road network, wherever possible.
https://www.hs2.org.uk/work-items/change-of-date-for-utility-works-on-a40-western-avenue/#msdynmkt_trackingcontext=e4f9999d-a774-40b2-a0dc-f81eaa1fc956

Update to tunnel segment deliveries by road

please note the responses from LBH at the foot of this notice

from HS2

We’re writing to let you know about some planned works that we will be carrying out in your area.

HS2 Works Notification: Tunnel segment deliveries by road.

We are writing to update you on how tunnel segments are delivered to our West Ruislip site. We normally use the rail siding for segment deliveries, but are currently unable to do so until a

safety audit has been completed.

To maintain supply of segments to build the new high-speed rail the tunnels, we will need them to be delivered to West Ruislip by road from Thursday 2 May 2024, using our approved lorry routes.

We are not sure how long we will need to make deliveries by road but we will keep you informed.

Lorry movements for segment deliveries will be included in the existing limit of 550 lorry movements a day.

Most tunnel segment deliveries will be during core working hours (Monday to Friday 8am to 6pm, Saturday 8am to1pm). However, there may be some HGV movements outside core hours.

The association checked with LBH and got this:

HS2/SCS approached LBH yesterday 30th  April as the Rail Siding at West Ruislip Portal is temporarily out of use which means that the overnight Trains carrying TBM Segments cannot deliver to West Ruislip Portal for up to the next 2 weeks.

HS2/SCS requested that LBH allow increased TBM Segment deliveries by road while there are no deliveries by Rail and LBH have allowed this to make sure there is enough TBM Segments being delivered to keep the TBMs tunnelling.

For context, each Train delivers 140 TBM Segments, while each lorry carries 3 TBM Segments, so deliveries by Rail are very much the preferred method in usual circumstances.

LBH have allowed in these exceptional circumstances that the TBM Segment deliveries by road be consented to take place over a 24hr period 7 days a week over the next 2 weeks (or hopefully sooner once the Rail deliveries commence again). 

In reality, with the logistical issues faced by the Haulier there is not likely to be more than 30 lorries each day delivering the TBM Segments by road. Please note that since Feb 2024 HS2/SCS had been allowed up to 24 TBM Segment deliveries by road each day between 8am & 10pm, so while there will be an increased timeframe to get the Segments delivered by lorry (24hrs a day) we would not expect much of an increase in overall numbers on the roads around Ickenham.

and this:

Just to add that if the project can’t get deliveries of segments then a major part of it comes to a standstill.

The consent has been given due to the exceptional circumstances.  The incident at the rails sidings appears on face value to be relatively minor but does require an investigation and a safety audit which has ruled out any further rail deliveries until that has been successfully concluded.  If anything, this shows how safety is paramount to the project which is a primary objective and supported. 

As said above, the ANL is not commensurate with the scale or nature of the request.  The Council has only consented to the additional movements for a short while, and because these are exceptional circumstances.  Not to consent it would cause excessive delays to project.  Given the limited increase in movements and the short time frame, on balance, the correct course of action was to allow the request subject to monitoring movements and minimising those outside core hours.   

The deliveries mentioned (24 per day) have been monitored with the majority coming inside core hours and on most days, 100% in the core hours.  

There is likely to be a change to the deliver patterns, albeit the project has indicated to a minimal extent, to service the TBMs whilst the rail deliveries are not operable.  

This is a large scale project, and incidents are bound to happen.  We are fighting hard to get HS2 Ltd to improve the comms; this ANL was not reflective of the situation and we have made our disappointment known. 

Enforcement of dropped kerbs

The Council provides a service for residents and businesses that find their access blocked by a motorist.

You will need to register your property if you have a dropped kerb – The Association’s General Secretary registered hers many years ago but was allowed to register again. This suggests that, since it is now an outsourced facility, previous registrations have not been carried forward.

details on https://www.hillingdon.gov.uk/dropped-kerb-enforcement

Spring into Spring at the URC!

Come Saturday 4th May the sun will be shining [terms and conditions apply] and we’ll be holding our Spring Forecourt Sale from 10am to 12 Noon, admission FREE.
There’ll be our famous plant stall, bric-a-brac, hundreds of books, toys and games and pretty well anything we are given, except clothes and shoes.
Inside there will be a friendly coffee morning with homemade cakes alongside the higher quality books, collectables and a table of small, quirky objects including an otoscope [look it up!], a miniature travelling tool set, an RAF medal ribbon and some rather fine WW2 Red Cross certificates.
Proceeds will go to the work of the church and to our external charities for this year, which are THE SMILE TRAIN and PAPYRUS [prevention of young suicide] so there are extra reasons for grabbing a bargain.
The date is a change from the one previously announced but the two later dates of 8th June and 7th September still apply.
If you have items to donate please bring them to the church on Friday 3rd May between 2pm and 6pm or ring Richard Piper on 01895 634348 for collection.
This is also the number for any enquiries or offers of help.
Our earlier Coffee Morning and Coin Mountain raised £158, so many thanks to those who contributed to that and we look forward to your continued support on 4th May and during the rest of the year.

Breakspear Road South today/tomorrow

    from HS2

    3rd Party works – 2-Way Traffic Lights on Breakspear Road South Sat 27/04 & Sun 28/04

    We have been made aware of some 3rd Party works on behalf of Affinity Water that will require the use of 2-Way Temporary Traffic Lights this weekend on Breakspear Road South near the junction with Tile Kiln Lane. 

    The works will be taking place on Sat 27/04 and may also carry on into Sun 28/04 but they will be completed as quickly as possible to minimise any delays.
     

    Notice of Extended Hours Working for Concrete Pours at West Ruislip Portal – Final Pour Scheduled for Tue 30/04

    HS2/SCS have received consent from LBH to carry out some long continuous concrete pours for the construction of the 2 Attenuation Tanks over extended hours within the West Ruislip Portal Site.

    These concrete pours are taking place over 3 different days with the 1st pour taking place on Tue 09/04 and the 2nd pour taking place Thur 18/04. After this there is now scheduled to be a final pour on Tue 30/04 but it is not expected to take as long as previously thought so should not require use of all of the extended hours up until midnight. SCS have been granted consent to carry out the pours between 6am and midnight on these dates