BRS now has a VAS sign

Following receipt of funding from the HS2 Road Safety Fund and following requests from residents, a Vehicle-Activated Sign (VAS) has now been installed on Breakspear Rd South near to the junction with Swakeleys Rd. If a vehicle approaches the Sign at a speed more than the 30mph Speed Limit on this road, the VAS Sign will illuminate and encourage the driver of the vehicle to ‘SLOW DOWN’.

This is in addition to a number of other VAS Signs that were installed in 2022 on roads in the north of Hillingdon to reinforce the reduction in Speed Limits on several roads in the area (a scheme also paid for from the HS2 Road Safety Fund).

Harvil Road realignment

From 9 October to 5 November, we will be carrying out utility works and construction activities to build and finalise the connection sections for the Harvil Road realignment.

The construction activities that need to be completed during the closure include:

  • Main water connections, including pressure testing
  • Street lighting & electrical installation
  • Highway & drainage construction
  • Resurfacing, white lining and installation of street furniture
  • Earthworks & fencing installation

To carry out the works safely, we will need:

  • a lane closure from 9 to 15 October, between the Dogs Trust and our site entrances (gate 2) and,
  • a road closure from 16 October to 5 November between Certas bellmouth and the Dogs Trust for 24 hours a day for the three week period.

Please see details of the works   https://www.hs2.org.uk/work-items/harvil-road-closure-october-2023/

From 9 October to 5 November 2023
Between 8am and 6pm Monday to Sunday
What to expect
Road closure and temporary traffic signage
The closure will remain in place until works are completed
Operatives in the work area, as well as barriers and plant vehicles to construct the new road
What we will do
Maintain access to your property at all times
Clearly sign post the diversion route
Keep disruption to a minimum

BRS – This weekend

The HS2/SCS works which required Night Time Road Closures of Breakspear Road South for the removal of the Bridge Deck Edge Protection attached to both sides of the newly built HS2 Bridge has now been rearranged and will take place this Saturday 02/09 & Sunday 03/09 with the Road Closed between 10pm to 5am on both nights from the Chiltern Bridge to the HS2 Bridge.

These works were postponed at short notice due to the late submission of the Environmental Consent from HS2/SCS to LBH, but LBH have now agreed to allow these programme critical works to take place this weekend so as not to further delay HS2 operations. The works were originally proposed to take 5 Nights to complete, but the works have now been condensed to be completed over 2 Nights, which is a positive for all parties concerned. Details below:

Traffic Management:

• Night Time Road Closures of Breakspear Road South over 2 Nights – Sat 02/09 & Sun 03/09 (Road Closed 10pm to 5am)
• Road Closed from Chiltern Bridge to HS2 Bridge
• Diversion Route via Swakeleys Road, Ickenham Road, Ruislip High Street, Breakspear Road

Activities:

• Carry out the removal of the Bridge Deck Edge Protection attached to both sides of the newly built HS2 Bridge
• Once this piece of work is complete, the new Bridge over Breakspear Road South is complete from a construction perspective

BRS – as you were

from HS2
We’re writing to let you know about a delay to some upcoming works in your local area.

A few weeks ago we let you know that from 29 August to 1 September 2023, we would be carrying out works along Breakspear Road South, on the new HS2 bridge to remove the timber structure from the deck edge on both sides of the bridge.

These works have been delayed. We will write to you again when we have confirmed dates.

A40 utility works

HS2 Works Notification: Utility works on A40 Western Avenue

We wrote to you in July 2023 about utility works on the A40 Western Avenue, which were scheduled from 31 July but did not go ahead.

We can now confirm that from 21 August to 24 November 2023, we will be carrying out the works to protect the main gas pipe below the A40 Western Avenue between Hanger Lane Gyratory and Gypsy Corner.

We will be digging a number of trenches along the road to reach the depth of the main gas pipe in order to replace the existing pipe with a plastic alternative.

To ensure the safety of the public and our staff, temporary changes will be in place on the A40 Western Avenue, as we carry out these works.

Please click here https://assets.hs2.org.uk/wp-content/uploads/2023/08/2308-ANL-Notice-of-planned-utility-works-on-A40-Western-Avenue-August-2023-2-1.pdf for more information and to read the works notice.

What we are doing
We will be carrying out works to protect the main gas pipe below the A40 Western Avenue between Hanger Lane Gyratory and Gypsy Corner. We will be digging a number of trenches along the road to reach the depth of the main gas pipe. The existing metal gas pipe will be replaced with plastic.
How this might affect you
To ensure the safety of the public and our staff, temporary changes will be in place on the A40 Western Avenue, these include:
• Removal of the central reservation
• Installation of a contraflow system on the East and Westbound Carriageway
• Bus stop and parking bay suspensions
• Closure of the Eastbound Carriageway overnight on 17 November and 29 October 2023
Duration of works
21 August to 24 November 2023
Works will take place during the day for up 12 weeks, with overnight works planned in phases
What to expect
Temporary traffic management will be in place between Gypsy Corner and Hanger Lane Gyratory
Central reservation will be removed before and reinstated after the main works on the A40
Upgrade the existing main gas pipe from metal to plastic
What we will do
Provide updates at hs2.org.uk/in-your-area/map
Hold online and in-person events during August and September 2023