Harvil Road lane closure 26-30 April

From HS2

Notice of lane closure on Harvil Road

Ground investigation and CCTV survey
We wrote to you previously to advise you that we would be carrying out utility works from 19 to 30 April 2021. However, we have rearranged these dates and the works will now take place from 26 to 30 April 2021. We will undertake ground investigation and survey of the drainage system on Harvil Road from the junction of Skip Lane, down to our southernmost gates. For safety reasons, we will need to close a lane.

Duration of works
From 26 to 30 April between 8am and 5pm
We may be on site for an hour before the start and/or end of each shift

What to expect
Traffic management, operatives, excavation equipment to take samples and measurements, and surveying equipment, (including a CCTV camera) Lane closures controlled by automatic signals supported by operatives during the busiest parts of the day

What we will do
Maintain access to your property at all times