HS2 plans extended working hours

From HS2

Works are ongoing at our sites at Harvil Road and Newyears Green Lane to build the new road realignment, the Copthall Tunnels and the conveyor system. Some of these works will need to take place during extended working hours.

From 7 July until 31 October 2021, we will be extending our working hours on our sites and will be undertaking work on site from 7am to 6pm, Monday through Saturday. This is an extension of our core working hours of 8am to 6pm Monday to Friday and 8pm to 1pm on Saturdays.