Breakspear Road South jiggery pokery

from HS2

What works are taking place?
In order to construct the railway, we need to supply electricity to our compounds and work sites. In order to complete the cable connection works that are currently underway at Copthall Road West we need to install a larger high voltage cable from Copthall Road West across Breakspear Road South to connect with the existing substation.

We expect these works to begin on Saturday 2 April 2022 and they will last until Thursday 14 April 2022. We will return to resurface the carriageway at a later date and will provide advanced notice of any resurfacing works as soon as a date has been confirmed.

Any Public Rights of Way will be maintained wherever possible. While works are taking place access will be managed by on site staff with signage and traffic marshalling for pedestrians.

Advance warning signage and traffic management will be put in place prior to the works taking place.

Please note works are ‘subject to change’. We aim to meet our planned working dates, but these can change due to the impact of the weather or programme changes. We will do all we can to keep you updated.

Duration of works
Work will be undertaken from: 2 April 2022 – 14 April 2022

Hours of work
Monday – Friday 7am – 7pm

What to expect
Temporary lane closure and traffic management
Some noise from the works
Welfare facilities provided by a mobile unit

What we will do
Inform you of any changes Manage any environmental impacts such as traffic and noise, reducing them wherever possible