Estimated Start Date
01/07/2021
Estimated End Date
31/03/2022
Work item details
What we are doing
Over the coming months we will be carrying out enabling works in the Harvil Road area. These works will allow us to prepare the area which is required for the temporary storage and treatment of the soil that will be removed from the tunnels, before they are placed in their final location.
Our initial works will include:
- Setting up security fencing and hoarding
- Delivery of equipment for the removal of topsoil
- Vegetation clearance, including brambles and hedgerows
- Preparation works to secure and divert a section of the U49 footpath around the works area