Breakspear Road South
HS2/SCS has detailed works on Breakspear Road South that are Programme Critical and must be completed over the next couple of months. The most urgent requirement is to install the Conveyor over Breakspear Road South so that the Conveyor can be connected to the back of the TBMs to carry the materials/spoil from the tunnelling on the Conveyor to the Treatment Area within the Gate 1 Site on Harvil Road. Less urgent but still required are works including a Utilities Trench across the road for the connection for the TBM water supply, a Concrete Pour for the deck of the new HS2 Bridge and Patch Repairs to Pot Holes around Chiltern Bridge area to HS2 Site entrance.
LBH has agreed to allow HS2/SCS to carry out Night Time Road Closures of Breakspear Road South from Wed 15/03 to Sun 19/03. The Road will be Closed from 10pm to 5am Wed 15/03 & Thur 16/03, and 10pm to 6am Fri 17/03, Sat 18/03 & Sun 19/03. There is also a Contingency Plan in place for following weekend (Night Time Closures 25/03 & 26/03) should this work not be completed.
Water Mains Repair works on A40 Western Avenue
LBH has been alerted to Water Main repair works for Affinity Water (approved by TfL as it is its road) that will close the Slip Road connecting the Polish War Memorial Roundabout with the westbound carriageway to the A40 Western Avenue.
The Slip Road will be closed from Tue 28/02 at 8am, with the Permit in place until Fri 03/03 at 4.30pm (but hopefully completed sooner).
From the Traffic Management Plan: traffic heading west will be able to exit the westbound carriageway at the Polish War Memorial Roundabout and continue southbound onto West End Road.