Harvil Road Final Road Closure – confirmed dates for Jan 2024

HS2/SCS have confirmed the dates for the Harvil Road Final Closures to complete the Realignment will now be from Mon 08/01/24 until Sun 28/01/24.

The Road Closure is split into 2 Phases:
• Phase 1 = Mon 08/01/24 to Sun 14/01/24 – 1 Week Road Closure at Skip Lane side
• Phase 2 = Mon 15/01/24 to Sun 28/01/24 – 2 Week Road Closure at Dogs Trust side

The Road Closures have been planned so there remains Access for the Skip Lane Businesses and the CERTAS Oil Depot at all times which is achieved by splitting down the Road Closure into 2 smaller parts.

Phase 1 – Road Closure at Skip Lane – Mon 08/01/24 to Sun 14/01/24
• Access for Skip Lane & Oil Depot from Dogs Trust side
• Civils Works Skip Lane
o Hillingdon street lighting works (excavation, ducting, sleeves, pavement, post installation)
o Electrical installation
o Road Drainage works / Tie-in works
o Traffic island construction
o Road marking & signage
o Kerb and pavement works

Phase 2 – Road Closure at Dogs Trust – Mon 15/01/24 to Sun 28/01/24
• Access for Skip Lane & Oil Depot from Swakeleys Road/Harvil Rd
• Civils Works Skip Lane
o Traffic Management re-arrangement
o Skip Lane sheetpiles cutting
o Road Drainage works / Tie-in works
o Earthworks – Backfill
• Civils Works Dogs Trust
o Hillingdon street lighting works (excavation, ducting, sleeves, pavement, post installation)
o Electrical installation
o Traffic island construction
o Surfacing / Road Construction
o Kerb and pavement works
o Road marking
o Safety barriers & Fencing installation

Bus Route U9 Diversion during Harvil Road Closures

TfL have confirmed that Bus Route U9 will run on Diversion during the Harvil Road Closures in Jan 2024.

A full Timetable will be in operation but the Buses will leave Uxbridge and go as far as A40 Swakeleys Roundabout before beginning their Diversion along the A40 to Denham Roundabout, then along the A412 North Orbital Road, then onto Moorfield Road, then Moorhall Road and then finally onto Harvil Road and continuing on the normal Bus Route towards Harefield.

Breakspear Rd South Night Time Lane Closure – Mon 27/11 from 10pm until 5am on Tue 28/11

LBH have provided consent for HS2/SCS to carry out some surveying of a Thames Water Foul Sewer Manhole which will require a Lane Closure of Breakspear Rd South at Night on Mon 27/11 from 10pm until 5am on Tue 28/11.

Details of works:
Night Time Lane Closure on Breakspear Rd South – Mon 27/11 from 10pm until 5am on Tue 28/11:
• The Lane Closure will be on the Southbound carriageway and there will be Traffic Lights in place to control the traffic flow
• 3-Way Traffic Lights with Heads on Northbound, Southbound and at HS2 Haul Rd Crossing
• Haul Rd Crossing Lights on demand – as outside of Core Working Hours very little HS2 traffic crossing Haul Rd expected

Reason for Works:
• Internal survey of Thames Water Foul sewer manhole involving confined space man entry