| Harvil Rd – Update on Water Commissioning works The Water Samples HS2/SCS sent off to Affinity Water recently to get the new Water Main cleared for Commissioning to the Live Network have been returned as successful so the Water Main can now be commissioned to the Affinity Water Network. To achieve this HS2/SCS will put up temporary Traffic Management on Harvil Rd near the Dogs Trust on Mon 18/12 between 10am and 11am so operatives can access the new Water Valves and activate the new Main. Please note this activity was supposed to take place on Fri 08/12 but moved to Thur 14/12 at the request of HS2/SCS. These works will be done using Stop n Go Boards to keep disruption to as minimum as is possible, and we expect the work to take less than the 1 hour period requested (about 15 to 20 mins). Newyears Green Lane Road Closure for Conveyor Removal – Mon 12/02/24 until Sun 18/02/24 HS2/SCS are planning a Road Closure of Newyears Green Lane from Mon 12/02/24 until Sun 18/02/24 while they remove the Conveyor that currently oversails Newyears Green Lane between the NSPA and Copthall North Sites. These works have been scheduled to take place during the School Half-Term Holidays (w/c 12/02/24) so that disruption to the Road Network can be reduced. HS2/SCS have requested a full 6 days to complete these works as the removal can only be done if the weather conditions allow a Crane to remove the Conveyor, but LBH have requested that these works be expedited as quickly as possible so that the Road Closure may not require all 6 days. the Diversion Route will be down Harvil Rd, Swakeleys Rd, Breakspear Rd South (and vice versa). The Hillingdon Refuse & Recycling Centre will be open as usual with access via Harvil Road only during this Road Closure. |