Confirmation of HS2 Working Hours over Christmas and New Year period
Please note that the HS2 Sites in Hillingdon will be closed over the Christmas and
New Year period for both HS2 Contractors SCS and Align. Further details below:
HS2/SCS
Close on Fri 22/12/23 to Tue 02/01/24
-Following LBH Sites: West Ruislip Portal, Breakspear Rd South, Newyears
Green Lane (NSPA), SSPA, Harvil Rd Gate 1 (Treatment Area), Harvil Rd
Gate 2 (Copthall Tunnel)
–Skeleton crew throughout Christmas period
-Return to work with a safety day on Tue 02/01/24
Close on Day Shift of Sat 23/12 to Late Shift on 03/01/24
-Tunnelling Team – includes TBMs and all above ground activities such as
Conveyors
-Skeleton crew throughout Christmas period
-Return to work Late Shift on Wed 03/01/24
HS2/Align
Close on Fri 22/12/23 to Tue 02/01/24
-Construction of Colne Valley Viaduct
-Skeleton crew throughout Christmas period for maintenance, Site safety and security
-Return to work on Tue 02/01/24