Final phase of Harvil Road closure

From Ickenham Residents

  Phase 2 – Road Closure at Dogs Trust – Mon 15/01 to Sun 28/01
  Access for Skip Lane & Certas Oil Depot from Swakeleys Road/Harvil Rd end
Please note there will also be Temporary Traffic Lights on the section between Shorthill Cottage & Skip Lane during the Road Closure  

Civils Works Skip Lane
– Traffic Management re-arrangement
– Skip Lane sheetpiles cutting
– Road Drainage works / Tie-in works
– Earthworks – Backfill  

Civils Works Dogs Trust
– Hillingdon street lighting works (excavation, ducting, sleeves, pavement, post installation)
– Electrical installation
– Traffic island construction Surfacing /
– Road Construction
– Kerb and pavement works
– Road marking
– Safety barriers & Fencing installation  
 

Update as of Friday 19/01
 
The update from the Construction Manager on Harvil Road is that works are still progressing well with Street Lighting still being installed, new Traffic Islands being installed and tarmacking and white lining carried out in some sections this week. LBH are very much in the loop on what is happening with these works, our Street Lighting Team are carrying out the new Street Lighting installation and once the works are complete they require LBH Highways Technical sign off before the new realigned road can be open for public use.
 
The extremely cold weather this week has not delayed progress and the road is still expected to be ready for opening by late Sun 28/01 as planned. There is an Inspection of the new Road next Friday 26/01 where LBH Highways will be requested to sign-off on the new road layout being able to be opened for public use.