| FROM HS2 We’re writing to let you know about some planned works that we will be carrying out in your area. From 11 March to 30 June 2024, we will be carrying out piling works at our Gate 2 site, in the area west of Breakspear Road South and north of the Chiltern Railways Line. These works are part of the construction of the eastern portal of the Copthall Tunnel. We do not expect any noise or vibration to disturbance nearby residents. Monitoring will be in place throughout these works. We will use water sprays to reduce dust generated by construction activities. For further information please see our works notification. https://www.hs2.org.uk/work-items/notice-of-piling-works-at-copthall-tunnel-site/ We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum. |