Harvil Road & Skip Lane works – Night Time Only (7pm to 5am) Mon 10/06 to Mon 24/06
HS2/SCS are undertaking some Night Time works on Harvil Road and Skip Lane between 7pm and 5am for 2 weeks from Mon 10/06 at 7pm until Mon 24/06 at 5am. There will be Traffic Management on Harvil Road consisting mostly of multiple Phases of 2-Way Traffic Lights and there will be Road Closures in place on Skip Lane. During each day the Traffic Management will be removed so there will be no impacts to users of Harvil Road or Skip Lane between 5am and 7pm each day of these 2 weeks.
Extended Hours TBM Segment deliveries by Lorry into West Ruislip Portal – until 12/07
Deliveries of TBM Segments by Railway have now resumed following the issue with the Rail Siding recently but due to ongoing issues with HS2/SCS securing any more than 5 slots per week to run Train deliveries, HS2/SCS will continue to transport TBM Segments by Lorry into West Ruislip to maintain TBM operations and build up a surplus of TBM Segments in the Segment Yard.
Recently LBH had allowed HS2/SCS to deliver TBM Segments on lorries into West Ruislip Portal over a 24/7 period, but this has now been scaled back to the initial Extended Hours so these TBM Segments on lorries can now be delivered Mon to Sat between 8am and 10pm. This agreement is in place until 12/07 and will be reviewed again at that time
River Pinn Realignment and Footpath & Footbridge Construction – May to Oct 2024
From 23/05 to 16/10 HS2/SCS will be carrying out the River Pinn Realignment works. This will involve installing a new Footbridge which will reconnect the U45, U47 and U46 Public Rights of Way and create a new footpath to replace the existing U47.
Extended Working Hours at Breakspear Rd South Site for Construction of Retained Embankments – June to Dec 2024
From 17/06 to 31/12 HS2/SCS will be constructing the 3 Retained Embankments which connect West Ruislip Portal to the Copthall Tunnel. To do this HS2/SCS have been consented extended working hours from 7am to 7pm Monday to Friday and 7am to 4pm on Saturdays.
During the construction of the Embankments (that are either side of the River Pinn & Breakspear Rd South HS2 Bridges as shown on the Map below (Follow the link)) there is expected to be 10,000 lorry loads of material brought into the Sites from Harvil Rd Gate 2 and across the Internal Haul Roads. Lorries that are unloading on the west side of Breakspear Rd South will exit onto Breakspear Rd South on the HS2 Approved Lorry Route, and lorries unloading on the east side of Breakspear Rd South will continue on the Internal Haul Road to exit at West Ruislip on that HS2 Approved Lorry Route.
HS2/SCS will be building the Embankments to the required height using machinery for delivery and placement of material and the compaction of placed material will be carried out using vibratory rollers.
LBH will be keeping close tabs on the lorry movements and have also not committed to the full duration of the works when signing the consent. At present LBH will keep these works on a trial basis and review them on an ongoing basis.
works notification https://www.hs2.org.uk/work-items/extended-working-hours-at-our-site-on-breakspear-road-south/#msdynmkt_trackingcontext=326387ab-2414-4c6d-b1ac-5e58193767c3