Latest HS2 updates

from HS2

·  Updated River Pinn Realignment and Footpath & Footbridge Construction – new completion date of 02/11
Update 17/10 – with the heavy rainfall that has been on and off over the past couple of months there have been lots of delays to these works caused by having to remove the Dam and Overpumping on several occasions due to the increased rainfall. As a result these works have now been extended and are hoped to be complete by Sat 02/11.
·  Postponed Road Closure of Skip Lane for Surveys of Utilities & Drainage – 10pm to 5am over 2 Phases between 26/10 to 30/10 (Phase 1) and 02/11 to 03/11 (Phase 2)
·  New Breakspear Road South junction Fine Bush Lane 3-Way Traffic Lights (Mon 28/10 to Sat 02/11 – Daytime only 8am to 6pm)