Harvil Road at New Chiltern Line Bridge – Night Time Road Closures over 4 Saturday Nights 30/11, 07/12 & 14/12 (9pm to 6am)
HS2/SCS have requested 4 Night time Road Closures on Harvil Road (between 9pm to 6am) on 4 consecutive Saturday Nights from Sat 23/11 until Sat 14/12. These works are to survey the Butt Welds underneath and on top of the new Chiltern Line Bridge over Harvil Road.
The work can only be done on a Saturday Night due to limited Railway Possessions being available and over 4 Saturday Night Shifts as there are a lot of Welds that must be checked.
Dates:
• 23/11/24 – 24/11/24 (9pm until 6am) – completed
• 30/11/24 – 01/12/24 (9pm until 6am)
• 07/12/24 – 08/12/24 (9pm until 6am)
• 14/12/24 – 15/12/24 (9pm until 6am)
Postponed Road Closure of Skip Lane for Surveys of Utilities & Drainage – 10pm to 5am over 2 Phases between 30/11 and 04/12 (Phase 1) and 07/12 and 08/12 (Phase 2 Contingency Shift).
•
• HS2/SCS were going to be carrying out Surveys of the Utilities & Drainage on the section of road between Certas Oil Depot and the old Skip Lane junction (by the old Harvil Rd Bridge over the Chiltern Line).
• The Road Closure has been postponed and will be rearranged in 2025.
• When the works do take place the Road will be Closed at Night between 10pm to 5am. These works will not affect users of Harvil Road and will only impact the Businesses that use Skip Lane.
•
New Evening opening of the Information Hub – Monday 25/11 and Monday 02/12 between 6pm and 8pm
• The Information Hub is located beside the entrance to the West Ruislip Portal HS2 Site off Ickenham Road (the white portacabin to the right hand side of the Site entrance):
• Please note there will be evening opening of the Information Hub on Monday 25/11 and Monday 02/12 between 6pm and 8pm.
• Residents are welcome to drop in without an appointment to discuss any issues they may have or find out progress on HS2/SCS works in Hillingdon