Latest HS2 updates

Breakspear Rd South – Road Closure under Railway Bridge for Culvert Replacement – Sat 05/04/25 to Sun 27/04/25 (3 Week Road Closure)
 
Following on from the Trial Holes under a 2 Week Road Closure from 29/07/24 to 11/08/24 HS2/SCS have finalised their design for the new Culvert to be installed near to the Chiltern Line Bridge on Breakspear Road South.
 
There will need to be a final Road Closure of 3 Weeks in duration to install the new Culvert and following talks between LBH and HS2/SCS it has been agreed that these works will now take place at Easter 2025. With a Road Closure of this length of time whenever it is programmed in will result in traffic disruption on local roads but LBH will work with HS2/SCS to minimise this as much as is possible.
 
Schedule of works:
 
•    Sat 05/04/25 to Sun 27/04/25 = 3 Week Road Closure (which would be the 2 weeks of the School Holidays plus 1 week afterwards)
 
•    LBH School Easter Holidays = start Fri 04/04/25 – back to School on Tue 22/04/25
 
•    Good Friday = 18/04/25 / Easter Sunday = 20/04/25 / Easter Monday = 21/04/25
 
With the School Holidays taking place from 04/04/25 to 22/04/25 the only works taking place outside of the School Holiday period would be the final week from Tue 22/04/25 to Sun 27/04/25 (4 normal School days plus Saturday & Sunday).