HS2/SCS has agreed with LBH that Breakspear Road South will be closed at the Chiltern Railway Bridge from Fri 03/10 at 8pm until Sun 05/10 at 8pm while the Conveyor Bridge that oversails the Highway is removed
The Conveyor Bridge carries the Conveyor system that was used to transport the TBM Spoil/Material over Breakspear Road South towards the Treatment Area at Harvil Road Gate 1. Now that both TBMs have completed their tunnelling between West Ruislip and Greenpark Way in LB Ealing the Conveyors are being removed and the Bridges that carry the Conveyor can also be removed.
These works will involve laying Matting on the road surface to protect it, then using a Crane to lower the Bridge to ground level before dismantling and removing it. The road would then be cleared with the Matting removed before reopening to the public.
These works had been scheduled for the last weekend of the school summer holidays in August but has been rescheduled at the request of HS2/SCS.