| 1 Completed Thames Water Tankering Operation on Harvil Road – finished 31/03 Thames Water have now completed the repairs to the burst sewer main within Uxbridge Golf Course and this has removed the need for Tankers to be parked on Harvil Road under Temporary 2-Way Traffic Lights as of 31/03. All Traffic Management has now been removed and traffic flow on Harvil Road is now back to normal. 2 New Night Time Railway Possessions for Drainage Repairs & Topsoiling Near Harvil Road – 30/03 to 04/04 & 07/04/ to 10/04 (11pm to 7am) On the Dates listed below HS2/SCS will be carrying out drainage repairs & topsoiling works under Railway Possessions at Night Time between 11pm to 7am within the Site near Harvil Road Chiltern Line Bridge: Mon 30/03 at 11pm to 7am on Tue 31/03 Tue 31/03 at 11pm to 7am on Wed 01/04 Wed 01/04 at 11pm to 7am on Thur 02/04 Thur 02/04 at 11pm to 7am on Fri 03/04 Fri 03/04 at 11pm to 7am on Sat 04/04 Tue 07/04 at 11pm to 7am on Wed 08/04 Wed 08/04 at 11pm to 7am on Thur 09/04 Thur 09/04 at 11pm to 7am on Fri 10/04 The works are not expected to be noisy, 3 Ongoing Road Closure of Breakspear Road South (Service Road) for Affinity Water Main Replacement – Phase 1 = 30/03 to 27/05 / Phase 2 = 16/06 to 24/07 Notice issued by LBH Highways incorrectly stated Road Closure of Breakspear Road South main carriageway Confirmation received from LBH Highways that only the Service Road will be closed (rather than main carriageway) in the following 2 Phases Phase 1 = 30/03/26 to 27/05/26 (8am to 5pm daily) – Breakspear Road South Service Road – House Number 64 to 114 Copthall Road West (note – junction of Copthall Road West & Breakspear Road South is |CLOSED during Phase 1 works) Phase 2 = 16/06/26 to 24/07/26 (8am to 5pm daily) – Breakspear Road South Service Road – House Number 2 to 42 (note – junction of Greenacres Avenue & Breakspear Road South Service Road is CLOSED during Phase 2 works) New Noise Barrier Installation at West Ruislip – 01/04 to 31/12 Piling ahead of the Installation of the Noise Barriers in now complete from Copthall Tunnel to West Ruislip. Installation of Drainage alongside where the Noise Barriers will be installed remains ongoing. From April 2026 the Noise Barrier Panels will begin to be installed Mon to Sat between 8am & 6pm |