Heavy loads arriving at West Ruislip in March
From HS2:
As part of the substation installation, we will have 2no. Electrical Voltage Transformers delivered to our site. These transformers will change the incoming voltage from 33kV down to 11kV so that we can eventually power the Tunnel Boring Machines at their required voltages.
Our transformers will be delivered at the weekend as they are coming directly from their delivery port, as they have been shipped from overseas. They are delivered through the night due to the load and will arrive at the West Ruislip portal in the morning in each instance. The works to install these transformers will be carried out across the following weekends:
Transformer 1 delivery: Saturday 13th March and Sunday 14th March 2021
Transformer 2 delivery: Saturday 27th March and Sunday 28th March 2021
At present, these dates are planned with our suppliers, however should there be any changes to the delivery due to freight passing the UK border we will update all residents and businesses accordingly.
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk.
Breakspear Road South 1 March single lane
From HS2:
To reduce the number of HS2 lorries using local roads we are building an internal haul road between our construction sites, crossing Breakspear Road South. To build the crossing point we will need to close Breakspear Road South from 12-15 March 2021. Closing the road and working over a single weekend will reduce the impact on traffic flow in the area and will allow us to work safely.
We will remove the existing road surface in order to construct wider junctions. Additionally, we will compact the area and resurface the carriageway, which will include new line markings and repositioning of concrete traffic barriers.
How this work might affect you
Breakspear Road South will be closed from9pm on12March to 5am on 15March2021.A diversion will be in place via Swakeleys Road B467/ High Road B466/ Ickenham Road/ High Street/Bury Street A4180/ Breakspear Road.
Duration of works
The road closure will be in place from9pmonFriday 12 March to5am on Monday 15 March2021
We may be on site for an hour before the start and/or end of the closure
What to expect
Breakspear Road South will be closed between the dates above
The use of equipment required to remove and reinstate the carriageway, including road planer, road roller, asphalt, line marking machinery and concrete barriers
We will use lights as needed and ensure that they face the work areas only
What we will do
Hoarding and screens will be used to reduce noise
Use water carts to keep dust to a minimum
Ensure that the diversion route is clearly signposted
Access will be permitted to the residences north and south of the road closure
HS2 to close Breakspear Road South 12-15 March
From HS2:
To reduce the number of HS2 lorries using local roads we are building an internal haul road between our construction sites, crossing Breakspear Road South. To build the crossing point we will need to close Breakspear Road South from 12-15 March 2021. Closing the road and working over a single weekend will reduce the impact on traffic flow in the area and will allow us to work safely.
We will remove the existing road surface in order to construct wider junctions. Additionally, we will compact the area and resurface the carriageway, which will include new line markings and repositioning of concrete traffic barriers.
How this work might affect you
Breakspear Road South will be closed from9pm on12March to 5am on 15March2021.A diversion will be in place via Swakeleys Road B467/ High Road B466/ Ickenham Road/ High Street/Bury Street A4180/ Breakspear Road.
Duration of works
The road closure will be in place from9pmonFriday 12 March to5am on Monday 15 March2021
We may be on site for an hour before the start and/or end of the closure
What to expect
Breakspear Road South will be closed between the dates above
The use of equipment required to remove and reinstate the carriageway, including road planer, road roller, asphalt, line marking machinery and concrete barriers
We will use lights as needed and ensure that they face the work areas only
What we will do
Hoarding and screens will be used to reduce noise
Use water carts to keep dust to a minimum
Ensure that the diversion route is clearly signposted
Access will be permitted to the residences north and south of the road closure
Planning updates 15-02-2021
New planning applications this week in UB10 8 then DR, EG, HB, PY and QA. New appeals in AG,BJ, SD and SF. Map link.
SCS & HS2 online face-to-face events
SCS and HS2 Ltd are holding one-to-one sessions on the 22 and 24 February.
These are intended to replicate engagement events they would have held in person but for Covid restrictions, and are aimed at local residents who have an interest in or concerns about the project and would like up to date information across a range of subject areas.
Registration is via Eventbrite, at this link: https://www.eventbrite.co.uk/e/one-to-one-virtual-events-hs2-works-in-hillingdon-and-northolt-tickets-141111996781
Planning updates 08-02-2021
New planning applications this week in UB10 8 then BQ, DF, EE, EU, HE, HJ, JJ, NG, NQ, QD, SG and SQ. New appeal in SQ. Map link.
Planning updates 01-02-2021
New planning applications this week in UB10 8 then AF and JF. New appeals in LU and SF. Map link.
Planning updates 25-01-2021
New planning applications this week in UB10 8 then BD, BQ, BT, DS, HE, PL, QA, QG and ST. No new appeals. Map link.
Harvil Road closure 13-21 February
FROM HS2
What we are doing
We need to construct a temporary highway to the side of the current Harvil Road to allow us to start work on realigning Harvil Road later this year, and begin to build two over bridges over the Chiltern and HS2 rail lines.
From 13 February we start work to construct the tie-ins to the current highway. We will need to use construction vehicles in the highway, and to dig a trial hole. To do this safely we need to close the road fully.
How this work might affect you
Harvil Road will be fully closed 24 hours a day from 13 to 21 February inclusive.
A diversion will be in place via Moorhall Road / A412 / A40 and will be
clearly marked.
Duration of works 13 to 21 February.
The working hours will run for 24 hours each day to reduce the closure of the road to one week
What to expect
Harvil Road will be fully closed 24 hours a day We will use lights as needed and we will ensure that these will face the work areas only
What we will do
We will ensure that the diversion is clearly marked throughout
Access to the Dogs Trust will be maintained throughout the road closure
Access will be permitted to the residences north and south of the road closure
The affected part of the road is from Skip Lane to the entrance to the Dog’s Trust
For more information:
https://hs2inhillingdon.commonplace.is/news/2021/01/19/hs2-works-notification:-notice-of-harvil-road-closure,-13-21-february-2021