Harvil Road closure

Harvil Road closed yesterday (sorry, I was away and couldn’t post here) and will be closed until 5th November.

A diversion will be in place via Moorhall Road / A412 / A40 and will be clearly marked.

Access to the Dogs Trust will be maintained throughout the works

See https://ickenhamresidents.co.uk/2021/10/12/update-on-harvil-road-closure-already/ for background detail.

Greenway surveying activity

from HS2

On 8 November 2021, our surveying team will be installing monitoring studs along The Greenway. This will help our team to monitor ground settlement in the area.

The monitoring studs will be installed on the kerbs along the Greenway. Our surveyors will use a tripod placed on the ground to take measurements and distances and they will be using hand tools so the noise from the activity should be minimal.

Our surveyors will carry out weekly visits after the installation to monitor ground settlement.

We will maintain access to footpaths and driveways for the duration of these works.

Duration of works
Installation on 8 November from 9am to 5pm
Weekly monitoring visits until 30 June 2022

What to expect
Two operatives in the work area, as well as handheld equipment and tripods
Weekly visits after the installation

What we will do
Maintain access to your property at all times

https://www.hs2.org.uk/work-items/notice-of-monitoring-equipment-installation-at-the-greenway/

HS2 updates

From HS2:

West Ruislip
The Western tunnel portal is currently being constructed. This is the launch site that the Tunnel Boring Machines that will construct the Northolt Tunnel section of the HS2 route.
https://www.hs2.org.uk/work-items/main-site-activities-in-the-west-ruislip-area/

Breakspear Rd Sth
Piling and other preparatory works are taking place to create strong ground foundations to allow for the construction of the Bridge over Breakspear Road South and the Bridge over the River Pinn.
https://www.hs2.org.uk/work-items/main-site-activities-in-the-breakspear-road-area/

Harvil Rd
Enabling earthwork activities are taking place to make way for the construction the Copthall Tunnel and the Northern & Southern Sustainable Placement Areas. We are also carrying out enabling works in preparation for the realignment of Harvil Road.
https://www.hs2.org.uk/work-items/main-site-activities-in-the-harvil-road-area/

Overnight works at West Ruislip

From HS2 Overnight works at West Ruislip – Meet our Engagement team


Apologies – our earlier notification about this gave a slightly misleading impression of the where the overnight works will be taking place. The map in this message shows where our Engagement team will be available on the dates given. For a map of the works, please click on the notification link below the map.
 
We’re inviting local residents to come and talk to our Engagement team about overnight works coming up at our West Ruislip site. The works are due to start on 25 October and finish on 17 December 2021.

If you have any questions or concerns about the works, you can talk to members of our Engagement team who will be at The Greenway near the U81 footpath on 19 October from 4-6pm and on 21 October from 1-3pm.

You can find out more about the works from our recent notification
 
For more information about HS2 in Hillingdon, please see the Hillingdon page of our website.

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk.  

Update on Harvil Road closure (already)

From Ickenham Residents’ Association
More information on Harvil Road closure. Hopefully we have the correct info this time.

Estimated Start Date
29/10/2021
Estimated End Date
05/11/2021

What we are doing
We need to construct a temporary highway to the side of the current Harvil Road to allow us to start work on the new road realignment of Harvil Road.

From 29 October to 5 November, we will start work to construct the tie-ins to the current highway. We will asphalt the temporary diversion along Harvil road, including kerbs installation, fencing works on the tie-in points and a new footpath will be constructed at the side of the road.

To safely carry out the works we need to close the road between Skip Lane and the Dogs Trust. During the road closure access will be maintained for residents and emergency services.

How this work might affect you
Harvil Road will be fully closed 24 hours a day from 29 October to 5 November.

A diversion will be in place via Moorhall Road / A412 / A40 and will be clearly marked.

Access to the Dogs Trust will be maintained throughout the works.

Duration of works From 8pm on 29 October to 8pm on 5 November We may be on site for an hour before the start and/or end of the closure

What to expect
Road closure, with operatives and barriers in place

Plant vehicles will be required to construct the new road diversion, footpath, including kerbs

What we will do
Maintain access to your property at all times. Diversion route will be fully signposted.

https://www.hs2.org.uk/work-items/hs2-works-notification-notice-of-road-closure-on-harvil-road/

Road closures and HS2 updates – bumper bundle

A40
With grateful thanks to all those who posted on Facebook
A 40 There will be night works to repair the Denham Viaduct as follows
Eastbound: From 10 p.m. to 5 a.m. 15th to 25th October Monday to Friday only
Westbound: From 10 p.m. to 5 a.m. 8th to 19th November Monday to Friday only

Harvil Road
HS2 Works Notification: Notice of road closure on Harvil Road

What we are doing
We need to construct a temporary highway to the side of the current Harvil Road to allow us to start work on the new road realignment of Harvil Road.
From 29 October to 5 November, we will start work to construct the tie-ins to the current highway. We will asphalt the temporary diversion along Harvil road, including kerbs installation, fencing works on the tie-in points and a new footpath will be constructed at the side of the road.
To safely carry out the works we need to close the road between Skip Lane and the Dogs Trust. During the road closure access will be maintained for residents and emergency services.

How this work might affect you
Harvil Road will be fully closed 24 hours a day from 29 October to 5 November. A diversion will be in place via Moorhall Road / A412 / A40 and will be clearly marked.

Access to the Dogs Trust will be maintained throughout the works.

Information on latest works

Update on weekly works at West Ruislip:
This weeks works at West Ruislip will consist of installation of site compounds and utility connections, commencement of excavation work and monitoring and soil removal.
https://www.hs2.org.uk/work-items/west-ruislip-works-update-11-10-2021/

Update on weekly works at Breakspear Road South:
This weeks works at Breakspear Road South will consist of using hydro breakers to trim concrete top from piling, earthworks and creating the foundation for the site car park as well as various monitoring surveys.
https://www.hs2.org.uk/work-items/breakspear-road-south-works-update-11-10-2021/

Upcoming works at Harvil Road and Copthall:
This weeks works at Harvil Road and Copthall consists of utility connection and highways preparation, piling works for the west portal of the Copthall tunnel and preparation works for a footpath diversion.
https://www.hs2.org.uk/work-items/harvil-road-copthall-works-update-11-10-2021/

Harvil Road Oct 19 and Nov 4

National Grid on behalf of HS2, will be a lane closure and a traffic light management system on Harvil Road on Tuesday 19 October between 9.30am and 3:30pm
This is to pull a protective net over the scaffold across the road.

Once the traffic management is in place the works should take no more than two hours to complete.

The same process applies on Thursday 4 November 2021 when we’ll remove the protective netting.
Access to residential properties or business premises will be maintained.

More info:
https://www.hs2.org.uk/work-items/national-grid-works-update-harvil-road-lane-closure/

BATTLE OF BRITAIN 80th ANNIVERSARY CONCERT

BATTLE OF BRITAIN 80th ANNIVERSARY CONCERT
Sunday 17th October 2021 at 7.30 pm
Battle of Britain Bunker Visitor Centre, Wren Avenue, Uxbridge, UB10 0GG

PROGRAMME TO INCLUDE:
Walton – Spitfire Prelude and Fugue
Coates – Dambusters March Bernstein – Great Escape March
Elgar – Nimrod from Enigma Variations
Parker/Charles – We’ll Meet Again

Adults £12, Concessions £10, Children 11-16 £5, under 11 Free
Reserve tickets by calling our Box Office 01895 674223,
Purchase through 01895 250615 or www.hillingdontheatres.uk or via an orchestra member

Details:
https://hillingdonphil.co.uk/concerts/

Preparing the way for the HS2 tunnels

From HS2

Estimated Start Date – 25/10/2021
Estimated End Date – 17/12/2021
From 25 October 2021 to 17 December 2021:
• Monday to Friday 8am to 6pm and 6pm to 4 am
• Two weekends during this period from Friday 6pm to Sunday 8pm
Exact dates will be confirmed via news alerts

What to expect
Excavation equipment and lorries
Additional staff on site outside core hours
Lighting will be required for the safety of the operatives

What we will do
Continue to monitor our work methods and minimise disruption
Instruct our staff to be mindful of our neighbours
Provide updates via news alerts

What we are doing
From 25 October 2021, we will start excavation works to prepare the base of the railway tunnels in the area shown on the map . We will be excavating the earth to prepare the area for the launch of the Tunnel Boring Machines and the creation of the portal area.  The earth excavated from this area will be stored temporarily at the golf course driving range. This stockpiled earth will then be used to landscape the area around the tunnels and the tunnel entrances once the construction works have been completed.

Excavation of area and placement on temporary storage area
• These works will take place in two shifts. This activity is needed to prepare the area for the concrete pours before the cold weather.

Continuous cement pour
• Two periods of fifty hours continuous pour of concrete is required to build two base slabs for the portal structure. The pour has to be continuous so that there is no loss to the structural integrity of the building.

Work mitigation

We will:
• Continue to monitor sound levels both inside and outside our site compound
• Carry out attended monitoring for the first two weeks to ensure noise and vibration levels are within our required limits
• Steel fixing works will only be done at the very bottom of the excavation at 11 meters below ground level
• Where possible, acoustic covers and blankets will be used
• Cutting and welding will only be carried out during the day (8am to 6pm)
• Dust mist cannons will surround the working areas
• Lighting will face away from residential properties.

We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum.

Engagement
Our engagement team will be available to discuss these works with the local community in the following ways:

– A presentation will be available on the HS2 in Hillingdon website page
– Staff will be available at The Greenway near the U81 footpath on the 19th of October between 4pm and 6pm, and 21st of October between 1pm and 3pm

HS2 updates

1  National Grid works update: Harvil Road lane closure

National Grid on behalf of HS2 will be managing traffic with a lane closure and a traffic light management system on Harvil Road on Wednesday 29 September between 9.30am and 3:30pm. Access to residential properties or business premises will be maintained.

More info:
https://www.hs2.org.uk/work-items/national-grid-works-update-harvil-road-lane-closure/

2  Update: Notice of lane closure at Harvil Road

What we are doing

We wrote to you in August to advise you that we would be carrying out utility connections until 30 September 2021. However, we will need additional time to complete these works which will be extended until the end of October 2021.

We will be carrying out utility surveys and utility connections along Harvil Road as part of the road realignment works. Temporary traffic management and lane closures will be required to ensure these works can be carried out safely.

We will work during off peak hours where possible to minimise disruption.

More info:
https://www.hs2.org.uk/work-items/update-notice-of-lane-closure-at-harvil-road-2/

local works maps
https://www.hs2.org.uk/work-items/main-site-activities-in-the-west-ruislip-area/
https://www.hs2.org.uk/work-items/main-site-activities-in-the-breakspear-road-area/

https://www.hs2.org.uk/work-items/main-site-activities-in-the-harvil-road-area/