HS2 works update w/c 22/11/25

Breakspear Road South Road Closure for Conveyor Bridge Removal – Fri 28/11 at 8pm to Sun 30/11 at 8pm
 
HS2/SCS have agreed with LBH that Breakspear Road South will be Closed at the Chiltern Railway Bridge while the Conveyor Bridge that oversails the Highway is removed These works have been rescheduled to take place on the weekend of Fri 28/11 at 8pm to Sun 30/11 at 8pm.
 
The Conveyor Bridge carries the Conveyor system that was used to transport the TBM Spoil/Material over Breakspear Road South towards the Treatment Area at Harvil Road Gate 1. Now that both TBMs have completed their tunnelling between West Ruislip and Greenpark Way in LB Ealing the Conveyors are being removed and the Bridges that carry the Conveyor can also be removed.
 
These works will involve laying Matting on the road surface to protect it, then using a Crane to lower the Bridge to ground level before dismantling and removing it. The road would then be cleared with the Matting removed before reopening to the public.
 

  • There will be no Emergency Services Access during this Road Closure due to overhead lifting operations on the carriageway.
  • The Pedestrian Crossing which runs diagonally underneath the Chiltern Line Bridge will be closed for the duration of this Road Closure (also due to overhead lifting).
  • Notices & Signage will be installed in advance to advise walkers of the Pedestrian Crossing Closure.
  • The Diversion Route has now been confirmed with HS2/SCS and is the usual Diversion via Swakeleys Road, Ickenham High Road, Bury Street, Breakspear Road 

Piling and Drainage Installation works for Noise Barrier in West Ruislip Embankment area – 28/07/25 to 27/03/26

From 28/07/25 to 27/03/26 HS2/SCS will be carrying out works to allow the construction of the Noise Barriers along the HS2 route between the Copthall Tunnel and West Ruislip Portal. These works will be happening during Core Hours only (Mon to Fri 8am to 6pm & Sat 8am to 1pm).

Update Nov 2025 – The Noise barrier Piling is being completed in 2 Phases. Please note that Phase 1 was completed in Oct 2025 and Phase 2 has now started in Nov 2025 (from w/c 17/11).
HS2/SCS will start by installing Concrete Piles to stabilise the ground, followed by the installation of Drainage Systems.

HS2 hiccup – update

FROM HS2

We informed you last week that we were halting works across the London tunnels sections of the route following a serious near miss incident at our site at Green Park Way. We have now begun a safe restart across some of these worksites following a comprehensive review of safety procedures and leadership.

From Monday, 20 October, we will safely restart: Utilities work in South Hampstead area in Camden; The delivery of tunnel pre-cast concrete segments to the Willesden Euro Terminal in Ealing; and Earthworks in the West Ruislip area in Hillingdon. Additionally, a railway possession led by Network Rail will be carried out in the Old Oak Common area over the weekend to facilitate preparatory works.
Additional measures are being implemented by our contractor, Skanska Costain STRABAG joint venture, to ensure the safety of the workforce.

More sites will restart in due course as we continue to implement additional safety measures which are considered necessary following the review. We will not compromise on safety and sites will only restart once we are satisfied that all appropriate measures are in place to protect the workforce.

We will continue to keep you updated on further safe restarts in your area.

HS2 hiccup

information update from HS2

Safety is our number one priority at Skanska Costain STRABAG joint venture (SCS) and across HS2. I’m writing to let you know that last week a serious incident occurred at our site at Green Park Way in Ealing. As a result, works are being safely halted across the London tunnels section of the route, including sites in Hillingdon. While no workers were physically harmed, SCS is undertaking a comprehensive review of safety procedures and leadership on their sites before a safe restart can take place.

Works will be brought to a safe stop and will remain on hold until we and HS2 are satisfied that all appropriate measures are in place to protect the workforce. We anticipate the review may take a number of weeks depending on the area and the type of work involved. We will continue to keep local communities updated

Footpaths near BRS: Have your say

PUBLIC FOOTPATHS U45, U46 AND U47 ADJACENT TO BREAKSPEAR ROAD SOUTH HAREFIELD

Diversion and stopping up of public footpaths U45, U46 and U47 (Public Footpaths Diversion and Stopping Up Order 2025).

79109/APP/2024/2760
The Public Consultation is open for comments until 29/10/25

https://planning.hillingdon.gov.uk/OcellaWeb/viewDocument?file=dv_pl_files%5C79109_APP_2024_2760%5C1MC04-SCJ_SDH-LS-DGA-SS05_SL07-531411_C02.pdf&module=pl

HS2 update

·  Postponed Breakspear Road South Road Closure – Fri 03/10 at 8pm until Sun 05/10 at 8pm (likely to be rescheduled to Fri 31/10 at 8pm to Sun 02/11 at 8pm – tbc)
Please note that these works have now been POSTPONED due to nesting birds found on the Conveyor Bridge Structure that cannot be removed as there are unhatched eggs. This means that both the original dates of 03/10 to 05/10 & the contingency dates of 17/10 to 19/10 cannot be achieved. HS2/SCS are looking at rescheduling these works and it is likely that the weekend of Fri 31/10 at 8pm to Sun 02/11 at 8pm will be the agreed date (with a further contingency date to be added). I will update you further next week on this matter.

New HS2 Planning Updates: 
The following Planning Applications are active and relate to HS2 works in Hillingdon. The aim going forward will be to provide concise information about active Planning Applications within this section which will be updated weekly. 
U81 – Stopping Up

  • Application to permanently Stop-Up (close) the U81 Public Right of Way is currently on hold with LBH Planning Team – ref: 75317/APP/2024/2074
  • Following public consultation there is strong opposition to the permanent Stopping-Up of the U81
  • Talks ongoing between HS2, DfT & LBH to look at any alternative routes or designs that might be feasible instead of proposed design that is deemed unsafe by LBH & Met Police
  • Once these talks have been completed and next steps are confirmed these will be communicated to residents 

Schedule 17 – Ickenham Access Road

  • Request for approval under Schedule 17 to the High-Speed Rail (London – West Midlands) Act 2017 for works relating to the shared Ickenham Access Road comprising of safety bollards, earthworks and a timber boom gate
  • LBH Planning Team – ref: 77816/APP/2025/2057
  • Decision due 23/09/25 (expected to be completed around 26/09)

Conveyor removal = BRS closure

from  HS2

From 8pm on Friday 3 October to 8pm on Sunday 5 October 2025, we will remove the conveyor bridge over Breakspear Road South, located between the Chiltern Railway bridge and the HS2 Breakspear Road South bridge.

These works will be carried out 24/7 over a whole weekend which will require a full road closure on a section of Breakspear Road South.

We will dismantle the conveyor bridge in sections using an excavator before lifting them out with a crane and transporting the sections off site. These works will be carried out 24/7 over a whole weekend.

Please note, these works can only be carried out under rail possession, therefore, to ensure completion we have a contingency date in place from 8pm Friday 17 October to 8pm Sunday 19 October.

New Years Green Lane closure

HS2 Works Notification:
Overnight road closure on Newyears Green Lane – 28 to 29 September 2025
From 9pm on Sunday 28 September to 5am on Monday 29 September, we will be carrying out overnight surveys on Newyears Green Lane, at the junction with Breakspear Road South.   To allow the surveys to be carried out safely, a section of Newyears Green Lane near the junction with Breakspear Road will be closed during the works. Diversion route will be sign posted.

HS2 update

For once some good news
If you weren’t already aware


Updated Harvil Road Resurfacing – Completed & Reopen Sat 23/08
 The LBH resurfacing of Harvil Road between the junction with Swakeleys Road and HS2 Gate 1 Site was completed ahead of schedule with the road being reopened for public use on Sat evening 23/08.
 The improvement in the road surface is immediately apparent and removes all of the issues with large pot holes on this section of road. There has also been works to improve the drainage network by cutting back & clearing the drainage ditches, clearing out the culverts and cutting back vegetation along the kerbside (so you can actually see the kerbs now).
Also
HS2/SCS Community Engagement Event at Ruislip Rugby Club – Tue 16/09 between 4pm & 7.30pm

 
There will be a Community Engagement Drop-In Event held by HS2/SCS at Ruislip Rugby Club on Tue 16/09 between 4pm & 7.30pm. There will be members of the Engagement Team & Technical Specialists at the Event to answer questions from residents on:  

  • Tunnelling Demobilisation works
  • Landscaping & Restoration works  

There will also be Drone Footage of the HS2 Sites in Hillingdon to show how construction is progressing

Address – Ruislip Rugby Club, West End Road, Ruislip, HA4 6DR 
There is no need to book for this Event – please feel free to attend between 4pm & 7.30pm

HS2 conveyor Pinn bridge removal

FROM HS2
We’re writing to let you know about some planned works that we will be carrying out in your area.

HS2 Works Notification: River Pinn conveyor bridge removal – 16 to 17 August 2025  

We previously informed you about the removal of conveyor bridges within our site at the West Ruislip Portal, following the completion of tunnelling in the area.  

From 16 to 17 August 2025, between 10pm and 5am, we will remove the conveyor bridge over the river Pinn, located between the Chiltern railway and the HS2 bridge.

We will dismantle the bridge sections before lifting them out with a crane.   

For safety, we need to complete this work overnight while no trains are running, due to the proximity to the Chiltern railway.