HS2 works update

Harvil Road Night Time Road Closures for Snagging Works – Mon 28/04 to Mon 19/05 
The 3 weeks of Night Time Road Closures of Harvil Road were completed on Mon 19/05 in time for the 5am opening of the road.  
All of the Snagging works along the new section of Highway between the Dogs Trust and HS2 Gate 1 have now been completed and the maintenance responsibility for this section of road has now been handed over from HS2 to LBH.
Construction of Tunnel Walkways from West Ruislip Portal – May 2025 to Feb 2026 
With the tunnelling now completed on the 2 tunnels between West Ruislip Portal and Greenpark Way Vent Shaft, the next stage is to build tunnel walkways inside the tunnels. There will be 2 walkways built inside each tunnel, a narrow walkway for maintenance access and a wider walkway to be used to safely evacuate passengers in case of emergency (once the railway is operational).  
In order to be build these walkways there will be concrete deliveries by lorry 24 hours a day, 7 days a week between the end of May 2025 and Feb 2026 to the West Ruislip Portal Site off Ickenham Road. 
The lorries will deliver ready-mixed concrete to electric pumps located behind a 2 metre high wall at the tunnel entrance (see map overleaf). The concrete will be pumped through a pipe into the concrete mixer truck and taken into the tunnels. The walkways will be built along the entire length of the tunnel using a Formwork system (Formwork is a temporary structure which shapes the walkway). The concrete is poured into the Formwork until it hardens, with the Formwork system being moved along the inside of the tunnel until the walkways are completed. 
HS2/SCS do not expect that these works will be noisy above ground as they will all take place within the tunnels, but there will be concrete deliveries by lorry 24 hours a day, 7 days a week. The Map below shows the location of the works:
Demobilisation works at West Ruislip Portal Site – March to Sept 2025 
With the 2nd Tunnel Boring Machine (TBM) Caroline completing her tunnelling journey to Greenpark Way Vent Shaft in April 2025, works will continue to remove tunnelling support structures inside and outside the tunnels at West Ruislip Portal Site. There will be demobilisation and removal works carried out for the following:  The conveyor structure – ongoing The launch chamber entrance – ongoing Rail siding – ongoing Gantry cranes and segment yard – ongoing Conveyor bridges – to be scheduled  
Removal of the Conveyor Structure – January to July 2025
HS2 have started dismantling and removing the Conveyor Structure by crane from within the West Ruislip Portal entrance from 02/01/25 with these works expecting to take until July 2025 to complete. The 1st Phase of these works will be removing the Conveyor Structure from the Downline Tunnel (as Sushila has completed her tunnelling) and then out into the Tunnel Portal at West Ruislip Now that TBM Caroline has completed tunnelling in April 2025 then the process will be repeated for the Upline Tunnel Then finally all of the remaining Conveyor Structure can be removed all the way from West Ruislip Portal along to the Treatment Area at Harvil Road Gate 1 Site. and Removal of Rail Siding at West Ruislip Portal – March to June 2025   The last Night Time delivery of TBM Segments by Railway to the West Ruislip Portal took place on 14/03 so now works have begun to decommission and remove the Rail Siding that accesses the HS2 Site from the main Chiltern Railway Line.   The track and ballast have now been removed, with the ballast being donated to the Bluebell Railway in West Sussex (see link below for more information):   HS2 donates 4,000 tonnes of ballast to Bluebell Railway | RailBusinessDaily   It is expected that the Rail Siding will be completely removed by June 2025.

HS2 works update

Updated Harvil Road Night Time Road Closures for Snagging Works – Mon 28/04 to Mon 19/05
 
Please note that the remainder of the Bridge Inspections on the HROC Bridge are no longer required as HS2 deem that they have enough data from those already completed to determine any remedial works required to the Welds going forward.
 
That means the current 3 Week Night Time Road Closures on Harvil Road as detailed below are now only to complete outstanding snagging works:
 

  • drainage cover repairs on the carriageway
  • white lining (weather dependant)
  • sealant works on the parapets on the new bridge along Harvil Road
  • snagging works along the footpath on Harvil Road to repair paving defects and cracks

 
There are Road Closures 7 Nights of the week, with extended hours on a Friday and Saturday Night Shift. I have detailed the dates and times of the Road Closures below:
 

Mon 28/04 at 11.59pm – Tue 29/04 at 5am Mon 05/05 at 11.59pm – Tue 06/05 at 5am Mon 12/05 at 11.59pm – Tue 13/05 at 5am
Tue 29/04 at 11.59pm – Wed 30/04 at 5am Tue 06/05 at 11.59pm – Wed 07/05 at 5am Tue 13/05 at 11.59pm – Wed 14/05 at 5am
Wed 30/04 at 11.59pm – Thur 01/05 at 5am Wed 07/05 at 11.59pm – Thur 08/05 at 5am Wed 14/05 at 11.59pm – Thur 15/05 at 5am
Thur 01/05 at 11.59pm – Fri 02/05 at 5am Thur 08/05 at 11.59pm – Fri 09/05 at 5am Thur 15/05 at 11.59pm – Fri 16/05 at 5am
Fri 02/05 at 9.30pm – Sat 03/05 at 6am Fri 09/05 at 9.30pm – Sat 10/05 at 6am Fri 16/05 at 9.30pm – Sat 17/05 at 6am
Sat 03/05 at 9.30pm – Sun 04/05 at 6am Sat 10/05 at 9.30pm – Sun 11/05 at 6am Sat 17/05 at 9.30pm – Sun 18/05 at 6am
Sun 04/05 at 11.59pm – Mon 05/05 at 5am Sun 11/05 at 11.59pm – Mon 12/05 at 5am Sun 18/05 at 11.59pm – Mon 19/05 at 5am

 
Update 16/05 – HS2/SCS have confirmed that works are progressing well and that the Road Closure has been in place each night as planned (see photos below). The works are on time to be completed on time with the last Night Shift scheduled to take place Sun 18/05 into Mon 19/05 at 5am:
Updated Demobilisation works at West Ruislip Portal Site – March to Sept 2025 
With the 2nd Tunnel Boring Machine (TBM) Caroline completing her tunnelling journey to Greenpark Way Vent Shaft in April 2025, works will continue to remove tunnelling support structures inside and outside the tunnels at West Ruislip Portal Site. There will be demobilisation and removal works carried out for the following:
 

  • The conveyor structure – ongoing
  • The launch chamber entrance – ongoing
  • Rail siding – ongoing
  • Gantry cranes and segment yard – ongoing
  • Conveyor bridges – to be scheduled

Updated May 2025 – Below is a Table & Map that shows the indicative demobilisation works programme over the next few months: 

Updated Decommissioning and Removal of Rail Siding at West Ruislip Portal – March to June 2025 
The last Night Time delivery of TBM Segments by Railway to the West Ruislip Portal took place on 14/03 so now works have begun to decommission and remove the Rail Siding that accesses the HS2 Site from the main Chiltern Railway Line. 
The sequence of the works begins with the removal of the track happening first, followed by the removal of the ballast. It is expected that the Rail Siding should now be completely removed by June 2025.

Proposed changes to bus routes

TfL is proposing changes to to bus routes 698, 697 and new school route 695

Consultation link: https://haveyoursay.tfl.gov.uk/route-698?cid=route-698

Proposals

To improve school bus services for The Douay Martyrs Catholic School, we propose to:

  • Introduce a NEW school bus route 695 between West Drayton and The Douay Martyrs Catholic School via Falling Lane and Cherry Lane
  • Reroute school bus 698 between Hayes and The Douay Martyrs Catholic School via Hayes Town and Bourne Avenue
  • The last stop on school bus routes 698, 697 and 695 would be at Swakeleys Drive, instead of Ickenham Station
  • School bus routes 698 and 697 would no longer stop at Hillingdon station in either direction

Benefits of the proposals include:

  • Faster journey times for West Drayton, Yiewsley and Hayes
  • More capacity where it’s needed
  • Encourage students to travel by bus, instead of car

(and even more buses parking up in Long Lane waiting to pick up students!!!)

HS2 event May 15

from HS2


We would like to invite you to a community drop in event.

• Date: Thursday 15 May 2025
• Time: 4pm to 7.30pm
• Venue: Ickenham Village Hall, 33 Swakeleys Road, Ickenham, Uxbridge UB10 8DG

Our engagement team and technical specialists will be available to update you and answer your questions on the following areas:
• Construction of Headhouse at West Ruislip
• Update on Tunnelling progress
We will use drone footage of HS2 sites in the area to show how construction is progressing.

For further details please follow this link. https://www.hs2.org.uk/events/hs2-scs-community-event-ickenham-village-hall/#msdynmkt_trackingcontext=bac77dec-f629-4c9c-9ed8-9a9554bb0000

BRS earthworks approaching completion

From HS2

We’re writing to update you about earthworks currently taking place at our site on Breakspear Road South.
HS2 Works Notification: Earthworks at the site on Breakspear Road South to be completed by 5 May 2025

We wrote to you in December 2024 to update you on works for the retained embankments construction at our site on Breakspear Road South, from 17 June 2024 to 31 March 2025.

These works have been delayed due to reduced availability of lorry deliveries. Our permitted lorry movements are limited, and we had to use some of them to move tunnelling materials off-site during this period of works.  In addition, heavy rain in January and February made it impossible to carry out the required compaction tests for the embankments. As a result, we now expect to complete the works by 5 May 2025.

For further details please follow this link.  https://www.hs2.org.uk/work-items/update-on-earthworks-at-the-site-on-breakspear-road-south/#msdynmkt_trackingcontext=556f0a93-da1a-41de-aed7-fcfe049a0300

HS2 updates

1    Breakspear Rd South – Road Closure under Railway Bridge for Culvert Replacement – Sat 05/04/25 to Sun 27/04/25 (3 Week Road Closure) 
Following on from the Trial Holes under a 2 Week Road Closure from 29/07/24 to 11/08/24 HS2/SCS have finalised their design for the new Culvert to be installed near to the Chiltern Line Bridge on Breakspear Road South. 
There will be a final Road Closure of 3 Weeks in duration to install the new Culvert and following talks between LBH and HS2/SCS it has been agreed that these works will now take place at Easter 2025. With a Road Closure of this length of time whenever it is programmed in will result in traffic disruption on local roads but LBH will work with HS2/SCS to minimise this as much as is possible.
 
Schedule of works:
•    Sat 05/04/25 to Sun 27/04/25 = 3 Week Road Closure (which would be the 2 weeks of the School Holidays plus 1 week afterwards)
•    LBH School Easter Holidays = start Fri 04/04/25 – back to School on Tue 22/04/25
•    Good Friday = 18/04/25 / Easter Sunday = 20/04/25 / Easter Monday = 21/04/25
With the School Holidays taking place from 04/04/25 to 22/04/25 the only works taking place outside of the School Holiday period would be the final week from Tue 22/04/25 to Sun 27/04/25 (4 normal School days plus Saturday & Sunday).

2    Diversion of U43 (adjacent to Breakspear Road South) – During Road Closure for Culvert Replacement – Sat 05/04/25 to Sun 27/04/25 
HS2/SCS are planning on using the upcoming 3 week Road Closure of Breakspear Rd South (around the HS2 Site/Chiltern Bridge area) between 05/04 and 27/04 to also do some de-vegetation works along where the U43 is currently diverted adjacent to Breakspear Rd South. 
While the de-vegetation works take place HS2/SCS plan to divert users of the U43 into their Site to make room for these works
3    Decommissioning and Removal of Rail Siding at West Ruislip Portal – March to May 2025 
The last Night Time delivery of TBM Segments by Railway to the West Ruislip Portal took place on 14/03 so now works have begun to decommission and remove the Rail Siding that accesses the HS2 Site from the main Chiltern Railway Line. 
The sequence of the works begins with the removal of the track happening first, followed by the removal of the ballast.  
It is expected that the Rail Siding will be completely removed by May 2025.
 
4    HROC Bridge on Harvil Road – Update Following Inspections  
HS2/SCS recently closed Harvil Road for 6 Nights per week (excluding Friday Nights) between midnight to 5am from 17/02 to 17/03 to carry out 170 Inspections of the Butt Welds on the underneath of the new Bridge (HROC) that carries traffic across the Chiltern Railway Line on Harvil Road. 
HS2/SCS have advised LBH that only about 50% of the total number of Inspections were completed during the recent Road Closures for a number of reasons: 
•    Cancelled Shifts due to Bridge Manufacturer Resourcing Issues
•    Cancelled or delays to Shifts due to Network Rail withdrawing/changing Railway Possession at short notice
•    Issues with working around Birds Nests
•    Each Inspection taking longer than expected  
This means that HS2/SCS will be requesting further Night Time Road Closures of Harvil Road around the beginning of May to complete these Inspections (they expect they will need another 3 weeks worth). 
HS2/SCS have to rehire the specialist Crane used for the Inspections which is not available for another month or so plus there is the Breakspear Road South Road Closure from 05/04 to 27/04 for the Culvert Replacement so any further Bridge Inspections would have to be scheduled after that. The results of the Inspections completed thus far are all being sent to HS2 Design House for review and analysis and this work is still ongoing so there are no results to be shared with LBH at present.

5    Decommissioning and Removal of Rail Siding at West Ruislip Portal – March to May 2025
The last Night Time delivery of TBM Segments by Railway to the West Ruislip Portal took place on 14/03 so now works have begun to decommission and remove the Rail Siding that accesses the HS2 Site from the main Chiltern Railway Line. 
The sequence of the works begins with the removal of the track happening first, followed by the removal of the ballast. 
It is expected that the Rail Siding will be completely removed by May 2025.
 
6    SCS Noise Barrier Testing near Breakspear Road South – June 2024 to June 2025
There will be Noise Barrier testing from late June 2024 until at least June 2025 for up to 24 hours a day, 7 days a week within the HS2/SCS Site to the west of the entrance off Breakspear Road South. Noise Barrier Testing commenced on 27/06/24 with the Generator and Actuator Instrument being used 24/7 to test the piles and the ground around them in the 1st Phase of testing.
A temporary embankment has been constructed in the area where Noise Barriers have been installed and the structural integrity will be tested. The scope of the testing is to confirm that the pile foundation and the structure will not have any significant changes due to Trains passing the Noise Barrier. The anticipated level of noise impact is expected to be minimal and will include the use of a generator which will power the instrument that will simulate the movement of the trains passing (the generator will be covered in acoustic barriers to minimise the noise). 
HS2/SCS are gearing up to commence the next Phase of testing, MFD (main fatigue and dynamic test) testing of the Noise Barrier Panels which is now expected to commence in April 2025 and be completed by the end of June 2025. A test setup of the Noise Barriers will be constructed like the image below. The panels will be fixed to the piles and secured by the torsion beam (which have already been tested) and continuous shaking of the panels will be undertaken 
Upon completion of the MFD testing of the piles, HS2/SCS will commence the Acoustic testing of the Noise Barrier Panels, the test acoustic barriers will be fitted with Acoustic Absorbers and rubber gap filler and Acoustic Steps. It is hoped that these tests will be carried out towards the end of June 2025.
The Trains using the HS2 Railway will not likely stop at night so the 24/7 testing is critical to simulate actual stress and strain on the Noise Barrier similar to the operational requirements and in reducing the duration of the test. This is fundamental to assuring Noise Barrier compliance. 

HS2 works update

a whole raft of stuff going on

1   HROC Bridge on Harvil Road – Update Following Inspections   
HS2/SCS recently closed Harvil Road for 6 Nights per week (excluding Friday Nights) between midnight to 5am from 17/02 to 17/03 to carry out 170 Inspections of the Butt Welds on the underneath of the new Bridge (HROC) that carries traffic across the Chiltern Railway Line on Harvil Road. 
HS2/SCS have advised LBH that only about 50% of the total number of Inspections were completed during the recent Road Closures for a number of reasons: 
•    Cancelled Shifts due to Bridge Manufacturer Resourcing Issues
•    Cancelled or delays to Shifts due to Network Rail withdrawing/changing Railway Possession at short notice
•    Issues with working around Birds Nests
•    Each Inspection taking longer than expected  
This means that HS2/SCS will be requesting further Night Time Road Closures of Harvil Road around the beginning of May to complete these Inspections (they expect they will need another 3 weeks worth). 
HS2/SCS have to rehire the specialist Crane used for the Inspections which is not available for another month or so plus there is the Breakspear Road South Road Closure from 05/04 to 27/04 for the Culvert Replacement so any further Bridge Inspections would have to be scheduled after that. The results of the Inspections completed thus far are all being sent to HS2 Design House for review and analysis and this work is still ongoing so there are no results to be shared with LBH at present. 
We will update you further once the dates have been confirmed for the further Night Time Road Closures.
2  Demobilisation works at West Ruislip Portal Site – March to July 2025 
With the 2nd Tunnel Boring Machine (TBM) Caroline due to complete the tunnelling journey to Greenpark Way Vent Shaft before the end of March 2025, works will continue to remove tunnelling support structures inside and outside the tunnels at West Ruislip Portal Site. There will be demobilisation and removal works carried out for the following: 
•    The conveyor structure
•    The launch chamber entrance
•    Rail siding
•    Gantry cranes and segment yard
•    Conveyor bridges 
3  Removal of the Conveyor Structure – January to July 2025
HS2 have started dismantling and removing the Conveyor Structure by crane from within the West Ruislip Portal entrance from 02/01/25 with these works expecting to take until July 2025 to complete.
From 02/01/25 to 02/02/25 this work will take place 24 hours a day, 7 days a week. To avoid overnight disturbance, HS2/SCS will carry out metal cutting and concrete breaking works from 8am to 10pm Monday to Saturdays and 10am to 4pm on Sundays. They will place acoustic blankets fixed to Heras fencing around the concrete breaking area to reduce noise.
•    The 1st Phase of these works will be removing the Conveyor Structure from the Downline Tunnel (as Sushila has completed her tunnelling) and then out into the Tunnel Portal at West Ruislip
•    Once TBM Caroline has completed tunnelling in March 2025 then the process will be repeated for the Upline Tunnel
•    Then finally all of the remaining Conveyor Structure can be removed all the way from West Ruislip Portal along to the Treatment Area at Harvil Road Gate 1 Site.
4 Decommissioning and Removal of Rail Siding at West Ruislip Portal – March to May 2025 
•    The last Night Time delivery of TBM Segments by Railway to the West Ruislip Portal took place on 14/03 so now works can begin to decommission and remove the Rail Siding that accesses the HS2 Site from the main Chiltern Railway Line. 
•    HS2/SCS are expecting to receive Network Rail approval to commence these works shortly, with the removal of the track happening first and then followed by the removal of the ballast. 
•    It is expected that the Rail Siding will be completely removed by May 2025.
 
5  TBM Segment deliveries by Rail and Lorry into West Ruislip Portal
•     
•    As stated above, the last Night Time delivery of TBM Segments by Railway to the West Ruislip Portal took place on 14/03 and with TBM Caroline due to complete her tunnelling journey to the Greenpark Way Vent Shaft in LB Ealing around 28/03 there should now be enough Concrete Tunnel Segments in the Segment Yard at West Ruislip Portal to complete the remainder of the tunnelling works. 
  
•    There is consent from LBH for HS2/SCS to bring in TBM Segments by lorry as a contingency when needed but only during Core Working Hours (Mon to Fri 8am to 6pm and Sat 8am to 1pm).
 
•    Those eagle-eyed among you may have spotted a small number of these deliveries by lorry during this week as SCS make sure they have enough TBM Segments on site for TBM Caroline to complete tunnelling next week.
6 Diversion of U43 (adjacent to Breakspear Road South) – During Road Closure for Culvert Replacement – Sat 05/04/25 to Sun 27/04/25
 
•    HS2/SCS are planning on using the upcoming 3 week Road Closure of Breakspear Rd South (around the HS2 Site/Chiltern Bridge area) between 05/04 and 27/04 to also do some de-vegetation works along where the U43 is currently diverted adjacent to Breakspear Rd South.
•     
•    While the de-vegetation works take place HS2/SCS plan to divert users of the U43 into their Site to make room for these works This allows them space to carry out the works in the area 

7 Working Hours at Breakspear Rd South Site for Construction of Retained Embankments – June 2024 to April 2025
•     
•    From 17/06/24 to 30/04/25 HS2/SCS will be constructing the 3 Retained Embankments which connect West Ruislip Portal to the Copthall Tunnel. These works were originally to be completed in Dec 2024 but have been delayed due to the very wet weather experienced over recent months and are now expected to be completed by the end of April 2025. 
•    At present this activity is only being carried out during Core Working Hours (Mon to Fri 8am to 6pm & Sat 8am to 1pm).  
•    During the construction of the Embankments (that are either side of the River Pinn & Breakspear Rd South HS2 Bridges as shown on the Map below) there is expected to be 10,000 lorry loads of material brought into the Sites from Harvil Rd Gate 2 and across the Internal Haul Roads. Lorries that are unloading on the west side of Breakspear Rd South will exit onto Breakspear Rd South on the HS2 Approved Lorry Route, and lorries unloading on the east side of Breakspear Rd South will continue on the Internal Haul Road to exit at West Ruislip on that HS2 Approved Lorry Route.
•     
•    HS2/SCS will be building the Embankments to the required height using machinery for delivery and placement of material and the compaction of placed material will be carried out using vibratory rollers.  
•    LBH will be keeping close tabs on the lorry movements during these works. 

8  •    24 Hour Working moving TBM Material for placement within The Copthall Tunnel – 24 hours a day, 7 days a week until May 2025 
•    HS2/SCS will be undertaking Day and Night work (24 Hour Working) at the Gate 2 Site on Harvil Road from March 2024 in order to build The Copthall Tunnel. These works will take place 7 Days a week and are currently included in the new Consent that will cover this activity up until the end of May 2025.

HS2 BRS update

FROM HS2

We’re writing to let you know about some planned works that we will be carrying out in your area.

HS2 Works Notification: Road closure on Breakspear Road South – 5 to 27 April 2025

From 5 to 27 April 2025, we will be carrying out works on Breakspear Road South, under a full 24-hour road closure north and south of the Network Rail bridge. 

During the road closure we will:

  • Remove and replace the culvert, including excavating a trench across the road to install the new drainage pipes
  • Cut sheet piles along the area of the HS2 Breakspear Road bridge
  • Install ditches by excavating and by clearing some vegetation and trees

The following traffic management will be in place:

  • A full road closure will in place to ensure that the work can be carried out safely.
  • A clearly signposted diversion route will be in place via Swakeleys Road B467/ High Road B466/ Ickenham Road/ High Street/ Bury Street A4180/ Breakspear Road.
  • Local access to residential properties will be maintained, however, there will be no through access for emergency services.

Two weeks of the closure will be within the Easter school holiday from 7 to 21 April 2025. We would like to apologise for any disruption or inconvenience these works may cause. For further details please follow this linkhttps://www.hs2.org.uk/work-items/breakspear-road-south-closure-5-to-27-april/#msdynmkt_trackingcontext=97b3e4d8-ff93-4abe-87c5-b0476433a3d5