Harvil Road delay explained

From R Connors :@ LBH

As you may be aware Harvil Road in Ickenham has been closed since the 08/01/24 while HS2 completed the Realignment of the new section of Harvil Road from the new junction for Skip Lane to the Dogs Trust (with the new straight section of road travelling over a new Chiltern Railway Line Bridge and a new HS2 Railway Line Bridge).

The works to complete the new Road were due for completion on Sunday 28/01/24 with the new Road opening for public use by midnight Sunday.

LBH Highways Delivery Manager Isaac Kwakye and myself attended an Inspection of the works this afternoon with a view of signing off the required technical documents for LBH to accept that the new Road is safe to be opened for public use.

While we were carrying out the Inspection we were alerted that HS2 Construction Compliance Certificates have not been signed off in time by HS2, and without this documentation in place HS2 cannot allow the new Road to open.

This is most frustrating for all concerned but especially for local residents and users of Harvil Road who have had to put up with so much disruption over the last few years due to HS2 works that have closed this road on many occasions.

Harvil Road will have to remain closed until this process is signed off by HS2 but we are hopeful that everything will be ready for the new Road to open for public use in time for Friday morning 02/02/24.

LBH Officers will push HS2 for this documentation to be completed as early next week as possible, and if that is the case we will endeavour to get Harvil Road open to the public sooner than the 02/02/24. I will keep you informed of the situation as this evolves next week.

Final phase of Harvil Road closure

From Ickenham Residents

  Phase 2 – Road Closure at Dogs Trust – Mon 15/01 to Sun 28/01
  Access for Skip Lane & Certas Oil Depot from Swakeleys Road/Harvil Rd end
Please note there will also be Temporary Traffic Lights on the section between Shorthill Cottage & Skip Lane during the Road Closure  

Civils Works Skip Lane
– Traffic Management re-arrangement
– Skip Lane sheetpiles cutting
– Road Drainage works / Tie-in works
– Earthworks – Backfill  

Civils Works Dogs Trust
– Hillingdon street lighting works (excavation, ducting, sleeves, pavement, post installation)
– Electrical installation
– Traffic island construction Surfacing /
– Road Construction
– Kerb and pavement works
– Road marking
– Safety barriers & Fencing installation  
 

Update as of Friday 19/01
 
The update from the Construction Manager on Harvil Road is that works are still progressing well with Street Lighting still being installed, new Traffic Islands being installed and tarmacking and white lining carried out in some sections this week. LBH are very much in the loop on what is happening with these works, our Street Lighting Team are carrying out the new Street Lighting installation and once the works are complete they require LBH Highways Technical sign off before the new realigned road can be open for public use.
 
The extremely cold weather this week has not delayed progress and the road is still expected to be ready for opening by late Sun 28/01 as planned. There is an Inspection of the new Road next Friday 26/01 where LBH Highways will be requested to sign-off on the new road layout being able to be opened for public use.
 

Harvil Road closure reminder

From Ickenham Residents. Harvil Road Final Road Closure – confirmed dates – 08/01/24 to 28/01/24
 
HS2/SCS have confirmed the dates for the Harvil Road Final Closures to complete the Realignment will now be from Mon 08/01/24 until Sun 28/01/24.
The Road Closure is split into 2 Phases: Phase 1 = Mon 08/01/24 to Sun 14/01/24 – 1 Week Road Closure at Skip Lane side Phase 2 = Mon 15/01/24 to Sun 28/01/24 – 2 Week Road Closure at Dogs Trust side The Road Closures have been planned so there remains Access for the Skip Lane Businesses and the CERTAS Oil Depot at all times which is achieved by splitting down the Road Closure into 2 smaller parts.
 
Phase 1 – Road Closure at Skip Lane – Mon 08/01/24 to Sun 14/01/24 Access for Skip Lane & Oil Depot from Dogs Trust side Please note there will also be Temporary Traffic Lights on the section between Dogs Trust & Skip Lane during the Road Closure  Civils Works Skip Lane Hillingdon street lighting works (excavation, ducting, sleeves, pavement, post installation) Electrical installation Road Drainage works / Tie-in works Traffic island construction Road marking & signage Kerb and pavement works Fencing  




 
 
Phase 2 – Road Closure at Dogs Trust – Mon 15/01/24 to Sun 28/01/24 Access for Skip Lane & Oil Depot from Swakeleys Road/Harvil Rd Please note there will also be Temporary Traffic Lights on the section between Shorthill Cottage & Skip Lane during the Road Closure  Civils Works Skip Lane Traffic Management re-arrangement Skip Lane sheetpiles cutting Road Drainage works / Tie-in works Earthworks – Backfill  Civils Works Dogs Trust Hillingdon street lighting works (excavation, ducting, sleeves, pavement, post installation) Electrical installation Traffic island construction Surfacing / Road Construction Kerb and pavement works Road marking Safety barriers & Fencing installation  

 

Bus Route U9 Diversion during Harvil Road Closures
 
TfL have confirmed that Bus Route U9 will run on Diversion during the Harvil Road Closures in Jan 2024.
 
A full Timetable will be in operation but the Buses will leave Uxbridge and go as far as A40 Swakeleys Roundabout before beginning their Diversion along the A40 to Denham Roundabout, then along the A412 North Orbital Road, then onto Moorfield Road, then Moorhall Road and then finally onto Harvil Road and continuing on the normal Bus Route towards Harefield.
   

TfL strikes

From TfL
Planned strike action will affect Tube services between Sunday 7 and Friday 12 January. If the strike action goes ahead:
• On Sunday 7 January, Tube services will close earlier than normal. Customers are advised to complete Tube journeys by 17:30
• From Monday 8 until Thursday 11 January, severe disruption is expected, with little to no service expected to run
• On Friday 12 January, Tube services will start later than normal with a good service expected by midday
London Overground, Elizabeth line, DLR, tram, bus and National Rail services are not involved in this strike action. Some services will be much busier than normal and affected by station closures where stations also serve London Underground lines. Queuing and one-way systems may be in place.

Plan ahead, check before you travel and leave more time for your journey.
For full details on strikes, visit our website

You may find it easier to walk or cycle some journeys. Our website has information on cycling in London, including our Santander Cycle Hire cycles and our cycleway routes, and walking options for journeys in zone one.

We are sorry for the disruption to your journey.

waste and recycling update

Recycle old, broken small electricals in a library near you

Don’t know what to do with your old electric toothbrush, hair styling appliances, Christmas lights or other small household electricals?

Pop along to one of our participating libraries where you can put old, broken small electricals in the pink collection bin, and we’ll recycle them for you. Ickenham is on the list

Find a participating library

HS2 Christmas working hours

Confirmation of HS2 Working Hours over Christmas and New Year period

Please note that the HS2 Sites in Hillingdon will be closed over the Christmas and

New Year period for both HS2 Contractors SCS and Align. Further details below:

HS2/SCS

Close on Fri 22/12/23 to Tue 02/01/24

-Following LBH Sites: West Ruislip Portal, Breakspear Rd South, Newyears

Green Lane (NSPA), SSPA, Harvil Rd Gate 1 (Treatment Area), Harvil Rd

Gate 2 (Copthall Tunnel)

Skeleton crew throughout Christmas period

-Return to work with a safety day on Tue 02/01/24

Close on Day Shift of Sat 23/12 to Late Shift on 03/01/24

-Tunnelling Team – includes TBMs and all above ground activities such as

Conveyors

-Skeleton crew throughout Christmas period

-Return to work Late Shift on Wed 03/01/24

HS2/Align

Close on Fri 22/12/23 to Tue 02/01/24

-Construction of Colne Valley Viaduct

-Skeleton crew throughout Christmas period for maintenance, Site safety and security

-Return to work on Tue 02/01/24