We’re writing to update you about earthworks currently taking place at our site on Breakspear Road South.
HS2 Works Notification: Earthworks at the site on Breakspear Road South to be completed by 5 May 2025
We wrote to you in December 2024 to update you on works for the retained embankments construction at our site on Breakspear Road South, from 17 June 2024 to 31 March 2025.
These works have been delayed due to reduced availability of lorry deliveries. Our permitted lorry movements are limited, and we had to use some of them to move tunnelling materials off-site during this period of works. In addition, heavy rain in January and February made it impossible to carry out the required compaction tests for the embankments. As a result, we now expect to complete the works by 5 May 2025.