HS2 works update w/c 22/11/25

Breakspear Road South Road Closure for Conveyor Bridge Removal – Fri 28/11 at 8pm to Sun 30/11 at 8pm
 
HS2/SCS have agreed with LBH that Breakspear Road South will be Closed at the Chiltern Railway Bridge while the Conveyor Bridge that oversails the Highway is removed These works have been rescheduled to take place on the weekend of Fri 28/11 at 8pm to Sun 30/11 at 8pm.
 
The Conveyor Bridge carries the Conveyor system that was used to transport the TBM Spoil/Material over Breakspear Road South towards the Treatment Area at Harvil Road Gate 1. Now that both TBMs have completed their tunnelling between West Ruislip and Greenpark Way in LB Ealing the Conveyors are being removed and the Bridges that carry the Conveyor can also be removed.
 
These works will involve laying Matting on the road surface to protect it, then using a Crane to lower the Bridge to ground level before dismantling and removing it. The road would then be cleared with the Matting removed before reopening to the public.
 

  • There will be no Emergency Services Access during this Road Closure due to overhead lifting operations on the carriageway.
  • The Pedestrian Crossing which runs diagonally underneath the Chiltern Line Bridge will be closed for the duration of this Road Closure (also due to overhead lifting).
  • Notices & Signage will be installed in advance to advise walkers of the Pedestrian Crossing Closure.
  • The Diversion Route has now been confirmed with HS2/SCS and is the usual Diversion via Swakeleys Road, Ickenham High Road, Bury Street, Breakspear Road 

Piling and Drainage Installation works for Noise Barrier in West Ruislip Embankment area – 28/07/25 to 27/03/26

From 28/07/25 to 27/03/26 HS2/SCS will be carrying out works to allow the construction of the Noise Barriers along the HS2 route between the Copthall Tunnel and West Ruislip Portal. These works will be happening during Core Hours only (Mon to Fri 8am to 6pm & Sat 8am to 1pm).

Update Nov 2025 – The Noise barrier Piling is being completed in 2 Phases. Please note that Phase 1 was completed in Oct 2025 and Phase 2 has now started in Nov 2025 (from w/c 17/11).
HS2/SCS will start by installing Concrete Piles to stabilise the ground, followed by the installation of Drainage Systems.

Wallasey Crescent Road Closure coming

LONDON BOROUGH OF HILLINGDON
TEMPORARY RESTRICTION OF TRAFFIC
(WALLASEY CRESCENT, ICKENHAM) ORDER 2026
ROAD TRAFFIC REGULATION ACT 1984 SECTION 14(1)
1. Hillingdon Council gives notice that to enable utility works to be carried out by Affinity Water and to prevent the likelihood of danger to the public it made this Order, which will temporarily close Wallasey Crescent from the junction of Copthall Road East to the junction of Swakeleys Road.
2. Diversion route will be in place via Copthall Road East, Swakeleys Road.
Nothing in the Order shall apply to prevent vehicular access to premises on or adjacent to the prohibited length of road insofar as access is reasonably practicable without interference with the said works.
3. The temporary restriction will be in operation between 08:00hrs on the 5th January 2026 to 17:00hrs, on the 27th March 2026 and to such extent as indicated by traffic signs prescribed by the Traffic Signs Regulations and General Directions 2016. Road users should assume that the closure has been put into effect only if traffic signs have been erected stating that the road
has been closed and the diversion route, if necessary is in place.
4. The Order, which is proposed will come into operation on 5th January 2026, will continue in force for eighteen months or until work to which it relates is completed. However, it is anticipated that the works will be completed within 12 Weeks.
Dated this 5 day of November 2025
Daniel Kennedy
Corporate Director of Residents Service

Parking in Beck theatre

The Cabinet Member for Community and Environment, in consultation with the Cabinet Member for Planning, Housing & Growth has considered the responses to the formal consultation for the proposed introduction of parking charges within The Beck Theatre Car Park, Hayes and has made the following decision:  
DECISION That the Cabinet Member for Community and Environment, in consultation with the Cabinet Member for Planning, Housing & Growth: Considered the objections received to the proposed parking charges for The Beck Theatre Car Park, Hayes; and Decided to introduce the parking charges as proposed.    
REASONS FOR DECISION The Beck Theatre offers a diverse programme including concerts, drama, comedy, dance, and children’s events. A new 15-year lease with Parkwood Leisure, with an option to extend for 10 more years, aims to preserve the theatre’s cultural identity, ensure financial sustainability without public subsidy, and boost community engagement. As part of the agreement, parking charges will be introduced at the theatre’s car park to align with other council-operated sites, helping offset operational costs. These proposals were agreed by Cabinet in May and became the subject of formal statutory consultation.  
ALTERNATIVE OPTIONS CONSIDERED AND REJECTED The Cabinet Member could have determined not to introduce the parking charges.   The Council will now complete the final part of the legal order making process to implement parking charges within this car park.

We will notify you as soon as we know when these charges will be effective
these will be    a maximum parking rate of £2.00 for four hours . Hillingdon residents are proposed to receive a 10% discount on the cost of parking by using the Hillingdon First Card. payment will be by the paybyphone app only

HS2 hiccup – update

FROM HS2

We informed you last week that we were halting works across the London tunnels sections of the route following a serious near miss incident at our site at Green Park Way. We have now begun a safe restart across some of these worksites following a comprehensive review of safety procedures and leadership.

From Monday, 20 October, we will safely restart: Utilities work in South Hampstead area in Camden; The delivery of tunnel pre-cast concrete segments to the Willesden Euro Terminal in Ealing; and Earthworks in the West Ruislip area in Hillingdon. Additionally, a railway possession led by Network Rail will be carried out in the Old Oak Common area over the weekend to facilitate preparatory works.
Additional measures are being implemented by our contractor, Skanska Costain STRABAG joint venture, to ensure the safety of the workforce.

More sites will restart in due course as we continue to implement additional safety measures which are considered necessary following the review. We will not compromise on safety and sites will only restart once we are satisfied that all appropriate measures are in place to protect the workforce.

We will continue to keep you updated on further safe restarts in your area.

HS2 hiccup

information update from HS2

Safety is our number one priority at Skanska Costain STRABAG joint venture (SCS) and across HS2. I’m writing to let you know that last week a serious incident occurred at our site at Green Park Way in Ealing. As a result, works are being safely halted across the London tunnels section of the route, including sites in Hillingdon. While no workers were physically harmed, SCS is undertaking a comprehensive review of safety procedures and leadership on their sites before a safe restart can take place.

Works will be brought to a safe stop and will remain on hold until we and HS2 are satisfied that all appropriate measures are in place to protect the workforce. We anticipate the review may take a number of weeks depending on the area and the type of work involved. We will continue to keep local communities updated

Footpaths near BRS: Have your say

PUBLIC FOOTPATHS U45, U46 AND U47 ADJACENT TO BREAKSPEAR ROAD SOUTH HAREFIELD

Diversion and stopping up of public footpaths U45, U46 and U47 (Public Footpaths Diversion and Stopping Up Order 2025).

79109/APP/2024/2760
The Public Consultation is open for comments until 29/10/25

https://planning.hillingdon.gov.uk/OcellaWeb/viewDocument?file=dv_pl_files%5C79109_APP_2024_2760%5C1MC04-SCJ_SDH-LS-DGA-SS05_SL07-531411_C02.pdf&module=pl

HS2 update

·  Postponed Breakspear Road South Road Closure – Fri 03/10 at 8pm until Sun 05/10 at 8pm (likely to be rescheduled to Fri 31/10 at 8pm to Sun 02/11 at 8pm – tbc)
Please note that these works have now been POSTPONED due to nesting birds found on the Conveyor Bridge Structure that cannot be removed as there are unhatched eggs. This means that both the original dates of 03/10 to 05/10 & the contingency dates of 17/10 to 19/10 cannot be achieved. HS2/SCS are looking at rescheduling these works and it is likely that the weekend of Fri 31/10 at 8pm to Sun 02/11 at 8pm will be the agreed date (with a further contingency date to be added). I will update you further next week on this matter.

New HS2 Planning Updates: 
The following Planning Applications are active and relate to HS2 works in Hillingdon. The aim going forward will be to provide concise information about active Planning Applications within this section which will be updated weekly. 
U81 – Stopping Up

  • Application to permanently Stop-Up (close) the U81 Public Right of Way is currently on hold with LBH Planning Team – ref: 75317/APP/2024/2074
  • Following public consultation there is strong opposition to the permanent Stopping-Up of the U81
  • Talks ongoing between HS2, DfT & LBH to look at any alternative routes or designs that might be feasible instead of proposed design that is deemed unsafe by LBH & Met Police
  • Once these talks have been completed and next steps are confirmed these will be communicated to residents 

Schedule 17 – Ickenham Access Road

  • Request for approval under Schedule 17 to the High-Speed Rail (London – West Midlands) Act 2017 for works relating to the shared Ickenham Access Road comprising of safety bollards, earthworks and a timber boom gate
  • LBH Planning Team – ref: 77816/APP/2025/2057
  • Decision due 23/09/25 (expected to be completed around 26/09)