| From HS2 HS2 Works Notification: Update on night works at West Ruislip We wrote to you in November last year, to let you know about night works taking place adjacent to the Golf Course at West Ruislip. In order to continue these works, we need to undertake some additional activities within what is known as a Network Rail ‘Possession’ which means that we can undertake works when the trains are not using the Chiltern Line track. These are generally overnight. Late on Saturday the 15th of January into the 16th of January we will be re-locating the hoarding line adjacent to the railway line, this will be done using hand tools predominantly and so is not expected to cause any inconvenience or disruption. There will be some vegetation clearance undertaken to facilitate this, which will be done as quietly as possible by hand. Ickenham Road HS2 Utilities Works January 2022: HS2 (through their contractors SCS) are undertaking a series of essential Utilities works in 2022 in advance of the Tunnel Boring Machine (TBM) travelling from near West Ruislip Tube Station under the ground in a tunnel to Old Oak Common in Acton. Any present Utilities along the route (such as gas, electricity, water and sewerage pipes) have to either be diverted or be renewed or reinforced so that the vibration from the movement of the TBM travelling underneath them will not cause breakages and damage to the existing pipework. In Ickenham Road these works have been split down into 7 Phases, with Phase 1 starting next Monday 10/01/22 where the central reservation on Ickenham Road outside of West Ruislip Tube Station will be removed. This is expected to take 2.5 weeks, and then the remaining Phases of works will follow on from each other consecutively. The details of these 7 Phases of works are as follows: Ickenham Road Utility Works (Utility diversion works including removal of the central reservation, excavation, installation and reinstatement of 12” Cadent gas main. Installation of Water valves and spiking of UKPN cable) Phase 1 – 10/01/22 to 26/01/22 – Traffic Management (TM) = Narrow Lanes (removal of central reservation) Phase 2 – 27/01/22 to 02/03/22 – TM = Contraflow, Footway Closure and 2 Stand-alone Pedestrian Crossings Phase 3 – 02/03/22 – 30/03/22 – TM = Contraflow, Footway Closure and Stand-alone Pedestrian Crossing Phase 4 – 31/03/22 to 20/04/22 – TM = Narrow Lanes and 2 Stand-alone Pedestrian Crossings Phase 5 – 21/04/22 to 25/05/22 – TM = Contraflow, Footway Closure and 2 Stand-alone Pedestrian Crossings Phase 6 – 26/05/22 to 29/06/22 – TM = Contraflow, Footway Closure and 2 Stand-alone Pedestrian Crossings Phase 7 – 30/06/22 to 05/08/22 – TM = Narrow Lanes and 2 Stand-alone Pedestrian Crossings (reinstatement of central reservation) HS2 has carried out community engagement activities with local residents, businesses and other key stakeholders such as TfL and local schools in the area to advise of these works. As there are no road or lane closures expected we do not foresee any delays to traffic movement in this area, and we have made it clear to HS2 that we expect Ickenham Road to remain open to 2-way traffic flow throughout the duration of these works, and access for pedestrians will also be maintained. Please note that LB Hillingdon Officers have been extensively involved in meetings with HS2 and their contractors to streamline these works as much as is possible in order to get the best solution available for our residents and road users in this area, and we will be closely monitoring the works when they happen to ensure that HS2 and their contractors keep to the agreed schedule and to expedite the works if at all possible. |
Category Archives: HS2
HS2 one-on-ones
| FROM HS2 We are holding virtual one to one sessions for you to learn more about HS2 works in Hillingdon and Northolt. HS2 and their contractors would like to invite you to book an appointment. The sessions are a chance to learn more about works in the Hillingdon and Northolt areas. The 15-minute appointments are available on: • Monday 10 January, from 4pm to 7pm When registering, please specify your area of interest and postcode. Topics available include: Works in your area Highways and traffic Noise and vibration Utility works Community engagement Other (please let us know if you have other queries) You can book a slot via the HS2 website, please click here: https://www.hs2.org.uk/events/hs2-scs-in-hillingdon-and-northolt-virtual-one-to-one-meetings-4/ Further joining instructions will be sent to all registered attendees closer to the time. |
HS2 Local Works Updates
FROM HS2
Works are ongoing at our sites at Harvil Road and Newyears Green Lane.
From 4 January 2022, we will be carrying out activities for the construction of the following assets:
• Treatment area south of the Chiltern Line railway
• New bridge over the Chiltern Line railway
• Copthall tunnel
• Northern sustainable placement area
• Harvil Road realignment
We will only carry out works agreed with the London Borough of Hillingdon and will adhere to the agreed working hours, noise and vibration limits.
Estimated Start Date 04/01/2022
Estimated End Date 26/03/2022
more info https://www.hs2.org.uk/work-items/works-update-at-our-sites-on-harvil-road-and-newyears-green-lane/
HS2 Works Notification: Utility works at High Road and Ickenham Road
We wrote to you recently to let you know that we would be carrying out utility relocation works from 6 December 2021 to 28 May 2022, near West Ruislip train station. However, we need to reschedule these works which will now take place from 4 January 2022 to 28 May 2022.
These works are to prepare for the start of tunnelling in 2022.
During the first phase of these works, we will be clearing some vegetation and removing the central reservation which will help to facilitate the second phase of the works and maintain two-way traffic flow at all times. Estimated dates are 4 to 21 January 2022.
During the second phase, we will be carrying out the main utility works which includes excavation, installation and reinstatement of the gas mains and installation of water valves. Estimated dates 24 January to 30 April 2022.
In the final phase we will reinstate the central reservation and pedestrian crossing. Estimated dates 2 to 28 May 2022.
Please see below for more information about locations and the works we will be carrying out over the next few months.
In order to carry out these utility works safely:
– a footpath diversion will be in place including a temporary pedestrian crossing either side of the work area
– the cycle path will be closed for the duration of these works
– the West Ruislip bus Stop S and Stop M will be suspended and temporarily moved to a safe location.
Your utility services will not be affected.
You may notice periods of increased noise during these works. We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to keep disruption to a minimum.
More info: https://www.hs2.org.uk/work-items/works-update-at-our-sites-on-harvil-road-and-newyears-green-lane/
Utility works at West Ruislip
From HS2
On the 29, 30 and 31 of December 2021, we will be carrying out steel fixing works on the tunnel portal area at our West Ruislip site.
These works will be done within our site boundary at 11 meters below ground level therefore, we do not anticipate any noise or disruption.
Steel fixing is the activity that takes place to create many of the steel support structures that are used in the construction of the railway, the work comprises a crane lifting materials into the excavation below ground and then operatives manually fixing these lengths of steel in place.
Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum. for more info
https://www.hs2.org.uk/work-items/notice-of-works-at-west-ruislip-portal-site/
Change to utility works at West Ruislip
From HS2
We wrote to you recently to advise you that from 6 December 2021 to 28 May 2022, we would be carrying out utility works near West Ruislip train station.
The main utility works, including the central reservation removal and utility relocation along High Road and Ickenham Road near West Ruislip station have now been rescheduled and will take place in January 2022.
We will notify you with the new date once confirmed.
HS2 Works Notification Update
| From HS2 We’re writing to update you about some planned works that have now been rescheduled. Harvil Road and Breakspear Road South • The culvert surveys that were planned for this week 29 November to 3 December on Harvil Road did not go ahead as planned. These works have now been rescheduled to take place the week commencing the 6th December 2021. Works will take place between 8pm and 5am on these dates. West Ruislip • We wrote you in September to advise you that we would be installing a dewatering system at our site at West Ruislip Portal. Part of these installation works will be carried out over two weekends, on 11 and 12 of December, and 18 and 19 of December 2021. Works will take place between 8am to 6pm on these dates. We will ensure that disruption is kept to a minimum. More information at https://www.hs2.org.uk/work-items/notice-of-overnight-culvert-surveys-at-harvil-road-and-breakspear-road-south/ |
Thames Water/Soldier’s Return
Thames Water update
We are working to divert our sewer to make way for the new HS2 railway. Following the London Borough of Hillingdon’s planning approval with planning conditions, we have received sign off of some of the conditions. This means we can plan to build the entrance point of the temporary haul road off High Road, Ickenham.
New road entrance
Subject to approval from the London Borough of Hillingdon, we will carry out work from Monday 13 December until Friday 24 December. This will be to construct a new road entrance off High Road, next to the entrance of The Soldiers Return.
The footpath will remain open for the duration of our works.
The High Road will remain open at all times, but we will need to close half of the northern lane. Traffic management will be in place to keep the traffic flowing.
Future work
We will not be working over the Christmas period and the site will close from 24 December until 4 January 2022.
When we restart our work, we will continue to construct the temporary road from the new access point to the Ickenham Green allotments.
More information: https://www.hs2.org.uk/work-items/notice-of-thames-water-work-3/
Breakspear Road South closure – update
| Breakspear Road South will be closed at the Chiltern Line Bridge from 12.01am Friday 26/11/21 for eight days while Network Rail carries out emergency repairs due to two bridge strikes in the last week. Two HGV lorries (large high-sided lorries) struck the side of the Chiltern Line Bridge, on 18/11/21 and again on 23/11/21. In the photos below, you will see visible damage to the underside of the bridge, including where brickwork has fallen onto the carriageway. Unfortunately there have been an increased amount of reported cases of HGV vehicles striking this bridge, with the Police confirming 15 incidents during this year alone. As a result Hillingdon Officers and Network Rail have worked together to facilitate the closure of the Breakspear Road South after the latest incident. This collaborative working will benefit our residents as we are now aware of the closure in advance (something that did not happen previously), and can communicate and plan for the closure. Officers have engaged with HS2 and its contractors to ensure there are no temporary traffic lights on the adjacent Harvil Road during this closure, and have instructed HS2 to make sure they take full advantage of this closure by bringing forward any planned works on Breakspear Road South while the closure is in place. Officers have requested that a Road Safety Audit is carried out as a matter of urgency (and paid for by HS2) to look at the location of the traffic lights in place on this section of Breakspear Road South. The traffic lights have been installed by HS2 to facilitate the movement of HS2 vehicles exiting the HS2 Site located just to the north of the Bridge, and are planned to be in place until at least 2024. Officers will continue to proactively explore all available options to eradicate these bridge strikes from happening, and will continue to work in collaboration with Network Rail and HS2 and their contractors to ensure the best possible outcomes for our residents should these incidents occur in the future |


HS2 update
| FROM HS2 We’re writing to let you know about some planned works that will be happening in your area. Works are ongoing at our site at West Ruislip to build the two Tunnel Boring Machines and the launch chamber area. From 6 December 2021, we will be carrying out the following activities: • Preassembly of Tunnel Boring Machine • Assembly of works area • Tunnel Boring Machine Assembly • Gantry assembly We will only carry out activities agreed with the London Borough of Hillingdon and will adhere to the agreed working hours, noise and vibration limits. You may notice periods of increased noise during these works. To minimise noise, acoustic screens and tents will be used. We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum. More info: https://www.hs2.org.uk/work-items/notice-of-assembly-works-for-tunnel-boring-machine/ |
Breakspear Road South closure
| Apologies, we have only just picked this up. We have been advised by Network Rail that last Wednesday 17th November, the Network Rail Chiltern Line Bridge, where it passes over Breakspear Road South, was struck by a Heavy Goods Vehicle approaching from the south. Network Rail has advised that they will use their emergency powers to close Breakspear Road South today 25 November from Breakspear Arms to Swakeleys Road. The closure will last for 7 days during which they will carry out the necessary examination and repairs. The HGV was not undertaking HS2 related works. Please note that this road closure will affect the current Celandine Way diversion as this route passes under the Chiltern Line Bridge. We may need to close this diversion for safety reasons |