Master Brewer: Judicial review granted

A little bit of good news.
We received this today from LBH

Permission given for judicial review
Hillingdon Council was given permission by the High Court on Wednesday 21 July to proceed with its judicial review of the Mayor of London’s decision to grant planning permission for the former Master Brewer site.   This means that the High Court is satisfied that the council has an arguable case.   The hearing of the case in the High Court is expected to take place later this year.

Colne Valley Park Festival Fortnight

We have been asked to circulate this to you:

We are delighted to share with you our Colne Valley Park Festival Fortnight details, which has an exciting programme of events and activities for everyone to enjoy across the whole Colne Valley. Please do share this post, as we would be thrilled for as many people to enjoy what is on offer as possible.

From Batchworth to Staines, Langley to Uxbridge, we are partnering with volunteer groups, organisations and charities to offer you a variety of guided walks, online talks, children’s activities and more for you to enjoy over the Festival Fortnight: Saturday July 24th to Sunday August 8th 2021

Follow our link: https://www.colnevalleypark.org.uk/colne-valley-festival-fortnight-2021/

To find out more, book on the events and get ready to explore, enjoy and discover the Colne Valley Park!


HS2 works August onwards

From HS2

Upcoming works
Works are ongoing at our sites at Harvil Road and Newyears Green Lane to build the new bridge over the Chiltern Line railway, the Copthall tunnel and the conveyor system.

From 2 August 2021, we will be carrying out the following activities:

• Piling works for the west portal of the Copthall tunnel
• Installation of the conveyor bridge over Newyears Green Lane
• Installation of support structures (abutments and wingwalls) for the new
bridge over the Chiltern Line railway
• Sheet piling at the MSD buildings off Breakspear Road South

We will continue to monitor noise, dust and vibration throughout our works and ensure that adequate measures are in place to minimise disruption.  Please see the following pages for more information about locations and the works we will be carrying out over the next few months.

1. Piling works for the Copthall tunnel
From 2 August to 18 September 2021, we will be carrying out piling work for the construction of the west portal of the Copthall tunnel.
The west portal pilling will be delivered using Continuous Flight Auger (CFA) techniques. CFA piling is when a continuous auger (hollow stem) is drilled into the ground to the required depth. Once the required depth is achieved, concrete is installed via the piling rig and through the hollow stem auger. The auger is then slowly withdrawn, and reinforced steel cages are installed. This method should not cause any disruption.

2. Road closure for conveyor bridge installation over Newyears Green Lane
From week commencing 2 August 2021, we will lift and install the conveyor bridge over Newyears Green Lane. A temporary road closure will be in place to ensure the installation can be carried out safely.
These works are dependent on weather conditions and we will therefore require two weeks after the start date as contingency to complete them. We anticipate the road closure to be in place for up to five days.  We will provide you updates at HS2inHillingdon.co.uk

3. Support structure installation
From 7 August 2021, we will be constructing the abutments and wingwalls, support structures for the new bridge over the Chiltern Line railway.
An abutment is a substructure unit located at the end of a bridge. Its function is to provide end support for the bridge superstructure. Wingwalls are also located at the ends of a bridge. Their function is to retain and provide support to the abutments.
For safety reasons, some of these works will take place between midnight and 6am, Saturday to Thursday, when trains are not running.

4. Sheet piling at MSD building

From 9 to 27 August 2021, we will be installing sheet piles at the MSD Building located off Breakspear Road South within our site.
Steel sheet piles will be installed in sequence along the planned perimeter and pressed into position. When arranged side by side, the sheet piles form a wall to provide earth support. We will not be expecting any disruption for these works.

Download information relating to these works

Extended working hours within our sites
Works are ongoing at our sites at Harvil Road and Newyears Green Lane to build the new road realignment, the Copthall Tunnels and the conveyor system. Some of these works will need to take place during extended working hours. From 7 July until 31 October 2021, we will be extending our working hours on our sites and will be undertaking work on site from 7am to 6pm, Monday through Saturday. This is an extension of our core working hours of 8am to 6pm Monday to Friday and 8pm to 1pm on Saturdays. We will only carry out activities agreed with the London Borough of Hillingdon and will adhere to the agreed working hours, noise and vibration limits. We will continue to monitor noise, dust and vibration throughout our works to ensure that we have adequate measures in place to minimise disruption. We appreciate your continued patience while we build HS2

“Hillingdon Hoard” webinar

Archaeologists working in Hillingdon on the HS2 project have uncovered a fascinating rare set of Iron Age potins, an early version of the coin, dating back to the 1st century BC. 

If you would like to find out more about this discovery, a free webinar on 19 July will explain all. You can register for it here: https://www.eventbrite.co.uk/e/festival-of-archaeology-hillingdons-hidden-history-tickets-157616668699

West Ruislip concrete breaking trials

From HS2:

At the West Ruislip site, we will be carrying out a 5-day trial of a machine that breaks down concrete into smaller reusable parts.

If this trial is successful, it will mean that the number of lorry movements required to transport concrete to and from site will be reduced and will remove a significant number of lorries from local roads.
for map and more info

https://www.hs2.org.uk/work-items/notice-of-equipment-trial-at-west-ruislip-site/

UPDATED – Weekday road closure at Breakspear Road South, 27 to 29 July 2021.

From HS2

From 27 to 29 July 2021, a road closure will be in place to complete the installation of crash barriers near the entrance to our site on Breakspear Road South.

A diversion will be in place via Swakeleys Road B467/ High Road B466/Ickenham Road/ High Street/ Bury Street A4180/ Breakspear Road.