New planning applications this week in UB10 8 then AG, PB, QG, QU, RU, SA, SD and SX. No new appeals. Map link.
Breakspear Road South restrictions from LBH
From LBH
LONDON BOROUGH OF HILLINGDON TEMPORARY RESTRICTION OF TRAFFIC (BREAKSPEAR ROAD SOUTH, ICKENHAM) ORDER 2021 ROAD TRAFFIC REGULATION ACT 1984 SECTION 14(1)
1. Hillingdon Council gives notice that to enable repair works to be carried out by O’Hara Bros and to prevent the likelihood of danger to the public it made this Order, which will temporarily close Breakspear Road South, Ickenham from Swakeleys Road to outside Breakspear Road.
2. Diversion route will be in place via Breakspear Road, Bury Street, High Street, Ickenham Road, High Road, Swakeleys Road and vice versa. Nothing in the Order shall apply to prevent vehicular access to premises on or adjacent to the prohibited length of road insofar as access is reasonably practicable without interference with the said works.
3. The temporary restriction will be in operation between 08:00hrs on the 15 th June 2021 to 17:00hrs, on the 20th June 2021 and to such extent as indicated by traffic signs prescribed by the Traffic Signs Regulations and General Directions 2002. Road users should assume that the closure has been put into effect only if traffic signs have been erected stating that the road has been closed and the diversion route, if necessary is in place.
4. The Order, which is proposed will come into operation on 15 th June 2021, will continue in force for eighteen months or until work to which it relates is completed. However it is anticipated that the works will be completed within 5 Days.
Dated this 18 day of May 2021 Perry Scott Corporate Director of Infrastructure, Building Services & Transport
Harvil Road lane closures 17 May to 30 September: Update
FROM HS2
Update:
We wrote to you in April to advise that we would be carrying out utility works from 17 May to 30 September 2021 and over two weekends. However, additional weekend working will be required.
From 17 May 2021, we will be carrying out utility surveys and utility connection along Harvil Road as part of the road realignment works. Temporary traffic management and lane closures will be required to ensure these works can be carried out safely.
We hope to reduce the duration of the lane closure by working additional weekends.
Planning updates 17-05-2021
New planning applications this week in UB10 8 then AA, EZ, JL, LN, NF, SX and UF. No new appeals. Map link.
Breakspear Road South – more work
From HS2:
From 26 May 2021, we will be carrying out enabling works at Breakspear Road South.
These works will help us to prepare the area for the temporary footpath diversion and the pedestrian bridge over the River Pinn. We will remove brambles and create a ditch to protect the area from potential flooding.
Planning updates 10-05-2021
New planning applications this week in UB10 8 then DG, DY, HJ, JW, NF, QD, QF and SX. New appeals in AJ and BD. Map link.
Breakspear Road South Extended work
HS2 Works notification: Update: Notice of works at Breakspear Road South, 9 – 14 May 2021
We wrote to you previously to advise you that we would be carrying out works from 7 to 9 May 2021. We need to extend the lane closure from 9 to 14 May 2021, in order to complete these works.
The road crossing at Breakspear Road South will become operational for our site traffic from 10 May 2021. The London Borough of Hillingdon has approved a speed limit reduction from 40mph to 30mph between Swakeleys Road and Breakspear Road, and to 20mph near the haul road crossing.
To ensure that this area is ready, we will be carrying out road and utility works along Breakspear Road South from 7 May 2021, in the area shown on the link below
These works will include the installation of concrete traffic barriers and line markings. Additionally, we will investigate the condition of the culvert system using a CCTV camera mounted on a small robot. Your utility services will not be affected.
Most of the work activities on the carriageways will be restricted to lane closures. However, for safety reasons there will be a full road closure needed for one night on 7 May.
Night time working along network rail
| from HS2 From 17 to 21 May 2021, we will be working along the Network Rail boundary to the south of the work compound. These works will take place at night when trains are not running. We will be extending the metal fencing and replacing sections in order to secure the site. |
Planning updates 05-05-2021
New planning applications this week in UB10 8 then AA, EJ, HP, JL, LR, NE, PN, PQ, QQ, QU and RW. No new appeals. Map link. Sorry for delay – Bank Holiday plus too busy yesterday.
Newyears Green Lane 17 May and June 1
From HS2
HS2 Notice of works at Newyears Green Lane
On 17 May and 1 June 2021, we will be carrying out ecological surveys along Newyears Green Lane.
A road closure is required between 8pm and 5am to ensure these works can be carried out safely.
Duration of works
17 May and 1 June 2021 between 8pm and 5am
We may be on site for an hour before the start and/or end of each shift
What to expect
Temporary traffic management
Ecologists and surveying equipment
What we will do
Maintain access to your property at all times