| FROM HS2 On 30 March to 4 April, 7 to 10 April 2026 between 11pm to 7am we need to complete some drainage repairs and topsoiling works within our site. These works need to be carried out overnight while the tracks below are not in use. We do not expect this work to be noisy, but you may notice workers and machinery on site outside of our normal working hours. For further information about these works, please follow this link. https://www.hs2.org.uk/work-items/overnight-works-at-harvil-road/#msdynmkt_trackingcontext=b4224e38-e377-43a4-bbd0-a48ddd8d0200 HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area. |
Category Archives: Events
HS2 update missing pix
Technical issues stopped the three images appearing in the previous post. Here they are:



HS2 update
HS2 update
| from HS2 We’re writing to let you know about some planned works that we will be carrying out in your area. HS2 Works Notification: Noise barrier installation at West Ruislip – 27 March to 31 December 2026 We previously informed you of our piling and drainage work within the noise barrier sites. We have now finished piling, while the installation of drainage systems is ongoing. From April 2026, we will begin to install the concrete noise barrier panels from Copthall Tunnel to West Ruislip Portal. There may be periods of noise from construction machinery while we carry out this work. We apologise for any disruption this may cause. For further details about these works, please follow this link. https://www.hs2.org.uk/work-items/piling-and-drainage-installation-works-for-noise-barrier-sites/#msdynmkt_trackingcontext=16d89118-73d7-48b5-ab11-4d5317ef0300 HS2 Works Notification Update: Flood compensation area works at Breakspear Road South – 1 April to 23 December 2026 We previously informed you that the flood compensation area works would take place from July 2025 to March 2026. However, most activities were paused during the winter period. We are now able to continue and expect the works to run until December 2026. We will be carrying out the following activities: Removal of the top layer of the soil Construction of permanent drainage Placement of subsoil and topsoil Seeding and landscaping Installation of permanent fencing around the area and U46 footpath For further details about these works, please follow this link. https://www.hs2.org.uk/work-items/construction-of-flood-mitigation-area-at-breakspear-road-south/#msdynmkt_trackingcontext=16d89118-73d7-48b5-ab11-4d5317ef0300 |
HS2 night time noise
| ADVANCE NOTICE OF New Network Rail Night Works between West Ruislip & Harvil Road – Sat 28/03 at 12.30am to Mon 30/03 at 5am There were several Noise Complaints received from residents towards the end of last week and over the weekend of 14/03 & 15/03 relating to very noisy works that could be heard coming from the West Ruislip area. The reported noise has been attributed to Network Rail, which has now confirmed that it had been carrying out significant track renewal, working at night removing, replacing, and tamping the track between West Ruislip and Harvil Road. Network Rail has now communicated details of the upcoming night works below to complete these works: Sat 28/03 at 12.30am to Mon 30/03 at 5am *** NETWORK RAIL HAS CONFIRMED THAT THESE WORKS WILL ALSO BE VERY NOISY SO THIS IS A NOTIFICATION TO NEARBY RESIDENTS TO MAKE YOU AWARE OF WHERE THE SOURCE OF THE NOISE WILL BE COMING FROM. |
Rural Activities Garden Centre meeting Friday 27th at 10:30
The Council made out the meeting was for ‘everyone’ and ‘residents’. IWe’ve been told it’s intended for gardeners only.
Rural Activities Garden Centre public meeting Friday 27th at 10:30
Take Action: Make Your Voice Heard
Now, for the first time, everyone in Hillingdon has a chance to show their support for RAGC staying at its uniquely safe and secure site in Yiewsley by coming to a residents’ meeting at RAGC. The meeting has just been announced by the Council and will take place on Friday 27th February starting at 10.30 am.
This is not a consultation as the Council has already made its decision, but with the local elections just over 2 months away, it would be a great time to show how much support RAGC has from across the borough.
PLEASE COME TO RAGC TO SHOW YOUR SUPPORT ON 27th FEBRUARY AND LET THE COUNCIL KNOW WHAT YOU THINK AT THEIR MEETING.
more info: https://fragc.uk/2026/02/21/ragc-meeting-for-residents/
This week’s BRS closure extended
We have been notified of a a delay to the Road Closure currently in place on Breakspear Road South that will require a 48 hour extension to the works. This will mean that the Road Closure will now be in place until Friday 20/02 at 7pm (it was due to be completed by Wed 18/02 at 7pm).
The reasons for the delay are shown below (please note this information has been updated on the LBH Website and will be communicated to residents by HS2 asap).
Breakspear Road South – 24/7 Road Closure over 5 Days – Sat 14/02 at 7am until Fri 20//02 at 7pm
HS2/SCS have agreed a Road Closure of Breakspear Road South that will take place 24 Hours a Day over a 7 Day Period from Sat 14/02 at 7am until Fri 20//02 at 7pm.
Update 17/02 – HS2/SCS are advising that the Trial Hole element of these works will not be completed in time for the originally planned reopening of the road on Wed 18/02 at 7pm and requested a further 48 hours on the Road Closure to complete the works (now reopening Fri 20/02 at 7pm).
The reasons behind the delay are detailed as being in part the ongoing wet weather conditions slowing things down, and the depth of the Sewer Connection that they have found to be at 3.3 metres. This was deeper than expected and thus required more time to locate in the footway and now HS2/SCS have to dig a trench across the width of the carriageway at this depth to make sure there are no unknown Services in the way for when the Sewer Connection is carried out.
These works have been scheduled to take place during the Feb 2026 School Half-Term to cause as little disruption as possible but we are aware there is never a good time to close this road.
Previously LBH had been informed by HS2 that all Road Closures on Breakspear Road South would be completed in 2025 but the following works are now required and unfortunately due to the methodology of the works they will require Full Road Closures to complete them:
• Rip-Rap Works – to install permanent paving and bollards to make safe the run-off area around a Drainage Swale
• To carry out a Trial Hole across the whole carriageway for a Sewer Connection that was previously removed during HS2 Enabling Works (this is a new instruction from HS2 not previously known about by SCS or LBH)
Please note – once the Trial Hole data is received, HS2/SCS will need to complete the Sewer Connection which will require a further Road Closure that they would look to request for the May School Half-Term or the School Summer Holidays.
BRS closure Feb 14-17
HS2 update
from HS2
The water treatment plant removal works are now ongoing until 28 February 2026. Works have been extended to accommodate access for other works.
These works will be 24/7 due to site constraints and the safety of the workforce. There will be lorry movements to remove the equipment during the day only. We will be emptying the treatment plant used to store water for our tunnel boring machines as it is no longer required. We will do this by using a hose connection into a silt buster system. Once emptied, we will disconnect and disassemble the plant and then remove from site during the day.
You may notice crane movements to lift the equipment for the water treatment plant and disassembly. Due to constraints on site some crane lifting may happen overnight. You may notice lights on site during nights, but we will position lights to avoid shining directly onto nearby properties. You may also hear white noise alarms during the day to ensure safety on site during the transportation of equipment. We will continue to monitor our working methods and noise levels to reduce disruption.
more info
https://assets.hs2.org.uk/wp-content/uploads/2026/01/HS2-SCS-25-1586-Update-to-247-working-to-remove-water-treatment-plant-at-West-Ruislip-Portal-Hillingdon_-February.pdf