Breakspear Road South closures (Part 2 of 2)

HS2/SCS has agreed with LBH that Breakspear Road South will be closed at the Chiltern Railway Bridge from Fri 03/10 at 8pm until Sun 05/10 at 8pm while the Conveyor Bridge that oversails the Highway is removed 
 
The Conveyor Bridge carries the Conveyor system that was used to transport the TBM Spoil/Material over Breakspear Road South towards the Treatment Area at Harvil Road Gate 1. Now that both TBMs have completed their tunnelling between West Ruislip and Greenpark Way in LB Ealing the Conveyors are being removed and the Bridges that carry the Conveyor can also be removed.
 
These works will involve laying Matting on the road surface to protect it, then using a Crane to lower the Bridge to ground level before dismantling and removing it. The road would then be cleared with the Matting removed before reopening to the public.
 
These works had been scheduled for the last weekend of the school summer holidays in August but has been rescheduled at the request of HS2/SCS.

Breakspear Road South closures (Part 1 of 2)

HS2/SCS has requested a Lane Closure managed with 3-Way Traffic Lights (plus pedestrian crossings) within its normal Haul Road Traffic Lights setup on Breakspear Road South from Fri 25/07 at 5am until Mon 28/07 at 5am.  In theory the Lane Closure would require an additional Phase to be added to the current Traffic Management setup (which is the long-term Haul Road Crossing plus Pedestrian Phase in place since 2021). 
The Traffic Management setup for the works Fri 25/07 at 5am until Mon 28/07 at 5am is as follows
  Traffic Head – Northbound Traffic Head – Southbound Traffic Head  – HS2 Haul Road (on demand) Pedestrian Crossings (on demand)  
The works are to install a temporary Bellmouth Access between the new HS2 Bridge and the Chiltern Line Bridge next to the Southbound carriageway, which will be used to assist removing the Conveyor System, install Drainage and Landscaping on the Embankment next to the Chiltern Line.
 
The Bellmouth Access once installed and operational will be in place until around Sept 2026 with a maximum of 10-15 vehicles using this Access per day. Once operational there will be a re-phase of the Traffic Management in this location with an additional Traffic Head added to the Bellmouth to allow safe exit onto the Highway (which should be off set with fewer vehicle movements required going across the Haul Road Crossing).
 
 

Update on borehole in West Ruislip station car park

We’re writing to update you about borehole works in West Ruislip Station car park.

HS2 Works Notification: Update on borehole works in West Ruislip Station car park 20 July to 25 July 2025

We wrote to you earlier in June 2025 about works to drill a borehole in West Ruislip Station carpark from 25 June to 3 July.  

We need to carry out a visual survey using handheld equipment. We will then drill a borehole in the ground. Once the borehole is complete, we will install a secure cover. The borehole will be located in between parking spaces so we can routinely access it to take readings. 

These works are now expected to take place from 20 July to 25 July.

During this work, we will suspend seven parking bays in the West Ruislip Station car park. 

For further details please follow this link.https://www.hs2.org.uk/work-items/notice-of-borehole-in-west-ruislip-station-car-park/#msdynmkt_trackingcontext=bd6996b4-147f-425d-ba5f-db300ffc0100

HS2 update



From HS2:

UPDATE We wrote to you recently to let you know that we would be carrying out the installation of noise barriers and drainage systems along the HS2 route from Copthall Tunnel to West Ruislip Portal sites, from 30 June 2025 to 27 March 2026. However, these works have been rescheduled, and we will now be starting from 28 July 2025. We will start by installing concrete piles to stabilise the ground, followed by the installation of drainage systems. Our working hours will be Monday to Friday 8am to 6pm and Saturday 8am to 1pm. You may notice periods of increased noise during these works. However, noise monitoring will take place throughout the works.  For further details about these work, follow this link. https://www.hs2.org.uk/work-items/piling-and-drainage-installation-works-for-noise-barrier-sites/#msdynmkt_trackingcontext=f4a19be3-2cf0-486b-95a3-8e9fbbe20100

Borehole in West Ruislip station car park

FROM HS2

We’re writing to update you about borehole works in West Ruislip Station car park. To support the construction of the new HS2 tunnels, we need to carry out groundwater monitoring along the line of route.   As part of this work, we planned to drill a new groundwater monitoring borehole in West Ruislip Station car park from 23 to 27 June 2025.   This work is now expected to take place from 25 June to 3 July 2025.   Seven parking bays will remain suspended in the car park until this work is completed.   For further details please follow this link. https://www.hs2.org.uk/work-items/notice-of-borehole-in-west-ruislip-station-car-park/#msdynmkt_trackingcontext=44bee33a-a885-4534-894d-0353d8cb0200  or this
https://assets.hs2.org.uk/wp-content/uploads/2025/06/HS2-SCS-25-1068-23062025-Update-borehole-West-Ruislip-car-park-June25.pdf

Another monster HS2 update

New Overnight Conveyor Bridge Removal at West Ruislip Portal – 14/06 to 01/07
HS2/SCS are now taking apart and removing the first of the Conveyor Bridges next to the Chiltern Railway Line at the West Ruislip Portal Site. These works need to be carried out overnight (between 10pm and 5am) due to requiring Railway Possessions to safely remove the Bridge.  
The Conveyor Bridge at the Rail Siding in West Ruislip Portal will be removed between 14/06 and 01/07 with the following dates for Railway Possessions confirmed between 10pm and 5am:  14/06 (10pm) to 15/06 (5am)              15/06 (10pm) to 16/06 (5am) 16/06 (10pm) to 17/06 (5am)              17/06 (10pm) to 18/06 (5am) 18/06 (10pm) to 19/06 (5am)              19/06 (10pm) to 20/06 (5am) 20/06 (10pm) to 21/06 (5am)              22/06 (10pm) to 23/06 (5am) 23/06 (10pm) to 24/06 (5am)              28/06 (10pm) to 29/06 (5am) 29/06 (10pm) to 30/06 (5am)              30/06 (10pm) to 01/07 (5am)  The Conveyor Bridges over the River Pinn and Breakspear Road South will be removed later in the summer 2025.
New Removal of the Concrete Lining around Pond 5 on the SSPA – Mon 23/06 to Fri 19/07
There will be works starting to remove the concrete lining around Attenuation Pond 5 within the SSPA site boundary near Breakspear Road South (Copthall Farm). 
These works will take place during core working hours (Mon to Fri 8am to 6pm & Sat 8am to 1pm) from Mon 23/06 to Fri 19/07.
The removal will be carried out in stages using hydro saw cutting, which helps manage dust during the process. There will also be an increased number of operatives and site vehicles accessing the area via the flood response gate (Copthall Farm HGV entrance). 
These works are necessary to allow landscaping to begin in that part of the site. The siltbuster system will remain in place throughout to support water management.
 New Piling and Drainage Installation works for Noise Barrier in West Ruislip Embankment area – 30/06/25 to 27/03/26
From 30/06/25 to 27/03/26 HS2/SCS will be carrying out works for the construction of the Noise Barriers along the HS2 route between the Copthall Tunnel and West Ruislip Portal. These works will be happening during Core Hours only (Mon to Fri 8am to 6pm & Sat 8am to 1pm). 
HS2/SCS will start by installing Concrete Piles to stabilise the ground, followed by the installation of Drainage Systems.  
The works will be carried out in 3 Phases: 
30/06/25 to 11/07/25 = Phase 1 – West of the Breakspear Road South to the HS2 Bridge
14/07/25 to 06/11/25 = Phase 2 – HS2 Breakspear Road South Bridge to HS2 River Pinn Bridge
22/09/25 to 27/03/26 = Phase 3 – East of the HS2 River Pinn Bridge to West Ruislip Portal
 New Lane Closure to build temporary access – Breakspear Road South – Fri 25/07 at 5am until Mon 28/07 at 5am
HS2/SCS have requested a Lane Closure managed with 3-Way Traffic Lights (plus pedestrian crossings) within their normal Haul Road Traffic Lights setup on Breakspear Road South from Fri 25/07 at 5am until Mon 28/07 at 5am
In theory the Lane Closure would require an additional Phase to be added to the current Traffic Management setup (which is the long-term Haul Road Crossing plus Pedestrian Phase in place since 2021). 
The Traffic Management setup for the works Fri 25/07 at 5am until Mon 28/07 at 5am is as follows   Traffic Head – Northbound Traffic Head – Southbound Traffic Head  – HS2 Haul Road (on demand) Pedestrian Crossings (on demand)  The works are to install a temporary Bellmouth Access between the new HS2 Bridge and the Chiltern Line Bridge next to the Southbound carriageway, which will be used to assist removing the Conveyor System, install Drainage and Landscaping on the Embankment next to the Chiltern Line.  
The Bellmouth Access once installed and operational will be in place until around Sept 2026 with a maximum of 10-15 vehicles using this Access per day. Once operational there will be a re-phase of the Traffic Management in this location with an additional Traffic Head added to the Bellmouth to allow safe exit onto the Highway (which should be off-set with fewer vehicle movements required going across the Haul Road Crossing).
Harvil Road Resurfacing – Full Road Closure – Mon 11/08 to Fri 29/08 (Provisional Dates) 
The long awaited LBH resurfacing of Harvil Road between the junction with Swakeleys Road and HS2 Gate 1 Site has now been provisionally scheduled to take place from Mon 11/08 until Fri 29/08
This will be a Full Road Closure in place 24 hours a day, 7 days a week in order to get this large area of road completely resurfaced.  
These are provisional dates that will be confirmed in the next couple of weeks once the Contractor and LBH Highways Team are confident that the works can be completed within this specified timeframe. If these works can be delivered across 19 days it will be a big reduction on the initially quoted 4 week Full Road Closure which would mean less disruption for users of Harvil Road in getting these essential works completed. 
During the Road Closure access maintained for residents of Harvil Road only during the Road Closure and the U9 Bus will have to be on Diversion.The confirmed dates and the Diversion Route will follow over the next couple of weeks.  
Change of Date Breakspear Road South Road Closure – Fri 03/10 at 8pm until Sun 05/10 at 8pm  
HS2/SCS have agreed with LBH that Breakspear Road South will be closed at the Chiltern Railway Bridge from Fri 03/10 at 8pm until Sun 05/10 at 8pm while the Conveyor Bridge that oversails the Highway is removed (Conveyor Bridge shown in the photo below). 
The Conveyor Bridge carries the Conveyor system that was used to transport the TBM Spoil/Material over Breakspear Road South towards the Treatment Area at Harvil Road Gate 1. Now that both TBMs have completed their tunnelling between West Ruislip and Greenpark Way in LB Ealing the Conveyors are being removed and the Bridges that carry the Conveyor can also be removed. These works will involve laying Matting on the road surface to protect it, then using a Crane to lower the Bridge to ground level before dismantling and removing it. The road would then be cleared with the Matting removed before reopening to the public. 
These works had been scheduled for the last weekend of the school summer holidays in August but have been rescheduled at the request of HS2/SCS.
 
 

Summer concert

Eastcote & Ruislip Choral Society Summer Concert:  A Little Light Music  

Saturday 5th July 2025 – 7.30pm 
Programme includes Gilbert and Sullivan songs, A Little Jazz Mass by Chilcott & excerpts from My Fair Lady  

Venue Douay Martyrs School, Edinburgh Drive, Ickenham, UB10 8QY  
Tickets £15 on the door, or from a choir member.  Under 12’s free.

Monster HS2 update

HS2 Works Notification: Update on overnight conveyor bridge removal at the West Ruislip site – 14 June to 1 July 2025
Tunnel construction from West Ruislip to Greenford completed in March and works are underway to remove tunneling support structures inside and outside the tunnels. 
We will be removing the first of the conveyor bridges at the West Ruislip Portal site, next to the Chiltern Mainline railway.
Due to the location next to the railway, we need to carry out these works overnight when trains are not running.
We will work overnight from 10pm to 5am on 14 June to 20 June, 22 June, 23 June and 28 June to 1 July.
We continue to monitor noise, dust and vibration throughout our works to ensure we have measures in place to minimise disruption.
Upcoming engagement
HS2 Information Hub. Visit us at the portacabin on the right of the West Ruislip Portal entrance, Ickenham Road. Mondays and Wednesdays, 2pm to 4pm. Specific sessions on these works on the following dates: 7 July and 4 August 2025.
Virtual Northolt Tunnel 1:1s. Every third Monday of the month. To sign up for a 1:1 meeting, please visit HS2 & SCS Virtual Drop-ins: Hillingdon Northolt Tunnel West Tunnelling Works
For further details and copy of notification letter, please follow this link.
You can find out more about what is happening in your area using the In Your Area pages of the HS2 website.
·  New Harvil Road Resurfacing – Full Road Closure – Mon 11/08 to Fri 29/08 (Provisional Dates)
he long awaited LBH resurfacing of Harvil Road between the junction with Swakeleys Road and HS2 Gate 1 Site has now been provisionally scheduled to take place from Mon 11/08 until Fri 29/08
This will be a Full Road Closure in place 24 hours a day, 7 days a week in order to get this large area of road completely resurfaced.  
These are provisional dates that will be confirmed in the next couple of weeks once the Contractor and LBH Highways Team are confident that the works can be completed within this specified timeframe. If these works can be delivered across 19 days it will be a big reduction on the initially quoted 4 week Full Road Closure which would mean less disruption for users of Harvil Road in getting these essential works completed. 
During the Road Closure access maintained for residents of Harvil Road only during the Road Closure and the U9 Bus will have to be on Diversion. 
The confirmed dates and the Diversion Route will follow over the next couple of weeks.  
There is also a scheduled Road Closure of Breakspear Road South from Fri 29/08 at 8pm until Sun 31/08 at 8pm but this will be dependent on LBH completing the resurfacing works by Fri 29/08.
 
New Breakspear Road South Road Closure – Fri 29/08 at 8pm until Sun 31/08 at 8pm
 
HS2/SCS have agreed with LBH that Breakspear Road South will be closed at the Chiltern Railway Bridge from Fri 29/08 at 8pm until Sun 31/08 at 8pm while the Conveyor Bridge that oversails the Highway is removed
The Conveyor Bridge carries the Conveyor system that was used to transport the TBM Spoil/Material over Breakspear Road South towards the Treatment Area at Harvil Road Gate 1. Now that both TBMs have completed their tunnelling between West Ruislip and Greenpark Way in LB Ealing the Conveyors are being removed and the Bridges that carry the Conveyor can also be removed. 
These works will involve laying Matting on the road surface to protect it, then using a Crane to lower the Bridge to ground level before dismantling and removing it. The road would then be cleared with the Matting removed before reopening to the public. 
This has been scheduled for the last weekend of the school summer holidays and also allows LBH to complete their planned LBH resurfacing works which will close Harvil Road prior to this from 11/08 to 29/08.
 
The Diversion Route has now been confirmed with HS2/SCS and is the usual Diversion via Swakeleys Road, Ickenham High Road, Bury Street, Breakspear Road
 
New Removal of the Concrete Lining around Pond 5 on the SSPA – Mon 23/06 to Fri 19/07
 
There will be works starting to remove the concrete lining around Attenuation Pond 5 within the SSPA site boundary near Breakspear Road South (Copthall Farm). 
These works will take place during core working hours (Mon to Fri 8am to 6pm & Sat 8am to 1pm) from Mon 23/06 to Fri 19/07. 
The removal will be carried out in stages using hydro saw cutting, which helps manage dust during the process. There will also be an increased number of operatives and site vehicles accessing the area via the flood response gate (Copthall Farm HGV entrance). 
These works are necessary to allow landscaping to begin in that part of the site. The siltbuster system will remain in place throughout to support water management.
 
New Piling and Drainage Installation works for Noise Barrier in West Ruislip Embankment area – 30/06/25 to 27/03/26
 
From 30/06/25 to 27/03/26 HS2/SCS will be carrying out works for the construction of the Noise Barriers along the HS2 route between the Copthall Tunnel and West Ruislip Portal. These works will be happening during Core Hours only (Mon to Fri 8am to 6pm & Sat 8am to 1pm). 
The Noise Barriers will be installed in the areas shown in the Red Box on the Map below. HS2/SCS will start by installing Concrete Piles to stabilise the ground, followed by the installation of Drainage Systems.  
The works will be carried out in 3 Phases: 
30/06/25 to 11/07/25 = Phase 1 – West of the Breakspear Road South to the HS2 Bridge
14/07/25 to 06/11/25 = Phase 2 – HS2 Breakspear Road South Bridge to HS2 River Pinn Bridge
22/09/25 to 27/03/26 = Phase 3 – East of the HS2 River Pinn Bridge to West Ruislip Portal
 
 

HS2 noise barrier creation

HS2 Works Notification: Piling and drainage installation works for noise barrier sites – 30 June 2025 to 27 March 2026

From 30 June 2025 to 27 March 2026, we will be carrying out works for the construction of the noise barriers along the HS2 route from Copthall Tunnel to West Ruislip Portal sites.

We will start by installing concrete piles to stabilise the ground, followed by the installation of drainage systems. Our working hours will be Monday to Friday 8am to 6pm and Saturday 8am to 1pm.

You may notice periods of increased noise during these works. However, noise monitoring will take place throughout the works.

For further details, please follow this link.https://www.hs2.org.uk/work-items/piling-and-drainage-installation-works-for-noise-barrier-sites/#msdynmkt_trackingcontext=26889400-a8ba-4723-931f-95b135d40200

and this  https://assets.hs2.org.uk/wp-content/uploads/2025/06/Piling-and-drainage-installation-works-for-noise-barrier-sites.pdf