HS2 is building a bat house to attract bats from properties scheduled for demolition.
Category Archives: HS2
Ruislip Golf Course hoardings
From HS2:
Update: Activity along the border
Work is continuing to place secure wooden hoarding along the Network Rail border to the south of our work site and then extend it along the southernmost edge of our works. The hoarding will ensure that the work site is both safe and secure. Preparatory works are still taking place during the day, and work on Network Rail land is only taking place at night when trains are not running. This activity is taking longer than expected due to unexpectedly limited number of working hours available next to the railway.
All lights needed for work activity will be placed so that they face away from the residential properties.
The side of the hoarding facing the properties in The Greenway and Hoylake Crescent will be painted dark blue. This colour has been agreed with Network Rail who need to ensure that the red, amber, and green lights are visible to their drivers’ sight lines. here will be a period where e will remove the part of the cutting. This will be done during the day.
Duration of works These works will continue until 18 September at the latest Working hours Day time activity will be between 8am and 6pm Night time activity will happen between 12.30am and 7.45am on Sundays and 5.30am all other mornings, when no trains are running We may be on site for up to an hour before and after these hours for preparation This work is progressing east to west. What to expect An excavator to remove the hoarding post foundations. All other activity will be using hand tools.
LBH wins appeal against HS2 arrogance
Friday 31 July: Hillingdon Council has successfully persuaded the Court of Appeal to overturn a High Court decision concerning the submission of planning applications by HS2 Ltd under the HS2 Act.
The council had refused to approve an application for HS2 works to be undertaken on a site in the borough of archaeological importance on the basis that HS2 Ltd had submitted insufficient information in support of it.
HS2 Ltd disagreed with the council’s refusal decision and challenged it, by appealing to the government, on the basis that it was not required to provide the information which the council required as it could instead rely upon a suite of non-statutory documents, known as Environmental Minimum Requirements, which would provide the council with the necessary assurances that the archaeological integrity of the site would be maintained and that HS2 Ltd would, if necessary, carry out its own future investigations as a means of safeguarding it.
The council sought a judicial review of the government’s decision to allow HS2 Ltd’s appeal but in December 2019, the High Court found in the government’s favour.
The Court of Appeal handed down its judgement today. It ruled that HS2 Ltd cannot rely upon the Environmental Requirements and that it has to provide sufficient information to the council in support of its planning applications. The council is under no obligation to determine the applications unless and until it receives such information. The Court of Appeal also frowned upon HS2 Ltd’s contention that it is permissible for it to carry out its own investigations, as part of the application process, saying that it would not have been the intention of Parliament to ‘set up a scheme which gave the appearance that HS2 Ltd was a judge in its own cause’. The government has also been ordered to pay the council’s legal costs of both the High Court and Court of Appeal cases.
Councillor Ray Puddifoot, Leader of Hillingdon Council, said: ”HS2 Ltd thought that HS2 could act with total impunity and just expect the Council to approve its planning applications without question. As the Court of Appeal has said, it cannot have been the intention of Parliament to allow HS2 Ltd to be a judge in its own cause. For the avoidance of doubt, this council will continue to challenge decisions that may harm our environment or the health and wellbeing of our people.”
https://hillingdon.gov.uk/article/5397/Hillingdon-Council-wins-HS2-planning-case-in-Court-of-Appeal
HS2 works including road closures
From HS2
Harvil Road daytime lane closures, weekdays 13 July to 7 August
We are starting to work on the building of a new section of Harvil Road, with a new road bridge over the Chiltern railway line. We will erect hoarding along the east side of Harvil Road. To build this hoarding our operatives will need to work in the road and, for the safety of the staff, we will need to close the southbound lane. To keep the closure as small as possible we will only close the lane where works are happening. These works will take place between 13th July and 7th August, between 8am and 6pm, Monday to Friday. You will still be able to travel through the area but may be asked to wait for a short time
Night time work at HS2 site in South Ruislip 13 July to 17 August
Night time work at HS2 site in South Ruislip 13 July to 17 August
We are starting work in the site compound on Network Rail land behind the old ARLA dairy site. It will consist of excavating and compacting earth into a small section of land to create a platform for hoarding to be installed. The work will take place at night time from 13 July to 17 August, Monday to Sunday 6pm to 8am, although the work will not be continuous.
Various road works – LBH and HS2
Road works Ickenham Road
We have been informed of Major works to supply HV power lines to the HS2 site stationed in Ruislip Golf Course. Works will commence 4th June 2020 for approx 12 weeks along Ickenham Road between Ruislip Golf Club and High Street Ruislip.
Given the traffic sensitivity of Ickenham road and traffic management required to accommodate these works, it is expected that these works will cause considerable disruption to Hillingdons road network.
In light of the above, these types of work would normally have been negotiated to be normally done during the school summer holidays however, given the extent (900meters), estimated duration and traffic management involved, it was deemed better to commence these works prior to the school summer holidays when traffic is still considerably less given the current climate surrounding Covid – 19, rather than waiting until School summer holidays when works would have extended well into September when the likelihood of local businesses and work streams resume back to normal.
Works will be done in two phases:
Phase one: Ickenham Road between Sharps Lane roundabout to High Street Ruislip.
Traffic management involved to accommodate these works will involve an eastbound closure of Ickenham road between Sharps Lane roundabout and High Street Ruislip, A hard closure of Sharps Lane at its junction with Ickenham Road along with 4 way temp lights at its roundabout of Wood Lane, Kingsend, & Ickenham Road.
Full diversions are in place to accommodate both closures.
Phase two – Ickenham Road between Sharps Lane and the entrance to Ruislip Golf course.
Traffic management will involve 2/3 way temp traffic lights.
Given the nature and sensitivity of Ickenham road these works will be monitored daily. HS2/UKPN have also been instructed to work seven days a week to expedite progress.
HS2 Updates 04-05-2020
HS2 Works Update: New utility surveys and ground investigations for Thames Water works from mid-May, and works restarting this week
Posted on May 4th 2020 by HS2 in Hillingdon
We are working closely with our construction partners to review the works on all our construction sites in line with Government and Public Health England (PHE) advice on dealing with Covid-19. The Government’s current Covid-19 strategy makes clear that construction activity can continue as long as it complies with this guidance, which you can see by clicking here.
The below works are going ahead as our contractors are confident that they can operate in line with PHE and industry guidance, protecting our staff and the communities in which they are working.
- Thames Water will be undertaking ground investigation works near the Greenway in Ickenham. To read more about this work please see the notification sent to residents by clicking here.
- Utility surveys on Ickenham Road – 26 to 28 May, to find out more please read the notification by clicking here.
- Utility surveys on Long Drive and Station Approach – 18 to 21 May, to find out more please read the notification by clicking here.
- Work will restart on the National Grid overhead powerline diversion. You can read more about this work on the dedicated page by clicking here.
- Archaeological surveys, including aerial surveys on land between Breakspear Road South and Harvil Road will resume in May.
For more please see our “Works in your area” page by clicking here.
HS2 Updates 28-04-2020
HS2 Works Update: New works and works restarting in Hillingdon
Posted on Apr 27th 2020 by HS2 in Hillingdon
We are working closely with our construction partners to review the works on all our construction sites in line with Government and Public Health England (PHE) advice on dealing with Covid-19. The Government’s current Covid-19 strategy makes clear that construction activity can continue as long as it complies with this guidance, which you can see by clicking here.
The below works are going ahead as our contractors are confident that they can operate in line with PHE and industry guidance, protecting our staff and the communities in which they are working.
Work on A412 and Moorhall Road
HS2 will be restarting a range of works just outside the London Borough of Hillingdon, including a temporary off-peak lane closure on the A412, near the Denham Water-Ski Club entrance. This is to allow for site set-up, archaeological and ecological works to take place including around Broadwater Lake. We will also be undertaking some work along Moorhall Road.
Dews Lane and Harvil Road area
Works have restarted at the compound to the west of Harvil Road and South of Dews Lane.
HS2 Land from Ruislip Golf Course to Breakspear Road South and Harvil Road
The U42 Bridleway diversion at Breakspear Road South is now open for public use.
Overnight works on the Chiltern lines in South Ruislip
We will be placing some monitoring equipment along the Chiltern Line and Central Line railways to ensure our construction does not impact on the lines. As all the equipment is self-powered there will be no need for any wires or cables to be placed in the area.
Works will comply with all safety rules with regard to working within the rail and tube environment. This being the case the work will take place from 00:01 to 08:00 in the early morning of Sunday 3 May. We will only use hand tools to reduce any noise impact.
HS2 Updates galore
HS2 Works Notification: Gas Main Diversion off Harvil Road and other works starting this week
Posted on Apr 14th 2020 by HS2 in Hillingdon
We are continuing to work closely with our construction partners to review the works on our construction sites in line with Government and Public Health England (PHE) advice on dealing with COVID-19. The Government’s current COVID-19 strategy makes clear that construction activity should continue as long as it complies with this guidance.
The below works are going ahead as our contractors are confident that they can operate in line with PHE and industry guidance, protecting our staff and the communities in which they are working.
Gas Main Diversion off Harvil Road
Following a winter shutdown period, Cadent is returning to its former compound off Harvil Road to complete work on the gas main diversion that it started last year. Works start this week and we expect work to be completed by June 2020. You can read more in this notification here.
Ruislip Golf Course
Delivery of aggregate to site will start from Wednesday 15 April, during usual working hours (8am to 6pm Monday to Friday and 8am to 1pm on Saturdays)
Land from Ruislip Golf Course to Breakspear Road South and Harvil Road
Surveys of land within HS2 sites and site hoarding from Tuesday 14 April.
Dews Lane and Harvil Road area
We are maintaining a security presence at their sites on Dews Lane and Harvil Road area. To enable this to continue there will be occasional deliveries to the sites of fuel and sanitation equipment. Servicing of welfare facilities and emptying of cess tanks will also take place.
Update on Completion of Work at Ruislip Rugby Club
We wish to update you on the current position with regards to the fields at Ruislip Rugby Club. Whilst the investigatory works within the fields have finished, we faced particularly difficult conditions due to the amount of rain that fell throughout January and February, water-logging the soil.
While we used matting to protect the fields as much as we could, some ruts occurred due to the movement of the vehicles and indeed the removal of the matting itself. We had been waiting for the ground to dry out sufficiently so that we could flatten out the area to remove the ruts that were left, however due to COVID-19 we paused activities at this site.
We are continuing to work closely with our construction partners to review the works on our construction sites in line with Government and Public Health England (PHE) advice on dealing with COVID-19. The Government’s current COVID-19 strategy makes clear that construction activity should continue as long as it complies with this guidance.
Our contractor is keenly aware of the need to finish the work at the club and we do fully appreciate that at this time many families are using the fields as the venue for their daily exercise. Please be assured that as soon as we are able to do so safely, we will return to the club and return the fields to their former condition.
HS2 Drop-in at Library tomorrow (10th)
Event: Drop-in at Ickenham Library, Tuesday 10 March, 2pm to 5pm
Posted on Mar 9th 2020 by HS2 in Hillingdon
Our regular HS2 drop-ins continue with a drop in tomorrow,10 March, at Ickenham Library from 2pm to 5pm. At our drop-ins you can speak to the local Community Engagement Manager along with engagement staff from the contractors.
The focus of this drop-in will be the main works contractor’s planned works for the area from Ruislip Golf Course to Breakspear Road South over 2020.
HS2 staff will also be available to answer any questions about the project or other works in Hillingdon.