Affinity Water will be carrying out connection works in Swakeleys Drive 15/8/21 to 18/8/21, between the junction with The Grove and No. 59.
Diversion via The Grove and Halford Rd
Affinity Water will be carrying out connection works in Swakeleys Drive 15/8/21 to 18/8/21, between the junction with The Grove and No. 59.
Diversion via The Grove and Halford Rd
From HS2:
At the West Ruislip site, we will be carrying out a 5-day trial of a machine that breaks down concrete into smaller reusable parts.
If this trial is successful, it will mean that the number of lorry movements required to transport concrete to and from site will be reduced and will remove a significant number of lorries from local roads.
for map and more info
https://www.hs2.org.uk/work-items/notice-of-equipment-trial-at-west-ruislip-site/
| from HS2 The U46 footpath diversion We are progressing to a stage in our works where we will be diverting a number of footpaths. These works will facilitate the completion of the internal haul road and help to keep as many vehicles off local roads as possible. Our first diversion is the U46 footpath, the short footpath that runs from the Celandine Way to Breakspear Road South near Oak Farm. The surface of U43 has been improved and extended and it currently progresses south behind the trees and emerges at a marked crossing point in Breakspear Road South. Please see map on link below. https://www.hs2.org.uk/work-items/notice-of-the-u46-footpath-diversion/ |
A virtual exhibition has been launched today
From HS2
Work item details
What we are doing
From 6 to 20 July 2021, we will be carrying out ground investigation along Ickenham Road and High Road near the West Ruislip train station, in the area shown on the map link below. This will help to inform our design decisions in the area. The ground investigation will involve the use of scanning equipment to identify utilities in the area. We will be excavating trial holes to take measurements and ground samples.
How the surveys might affect you
Due to the location of the utility surveys, footpath diversion will be in place and the cycle path will be closed for the duration of these activities. This is to ensure that the surveys can be carried out safely.
There will be no disruption to your utility services.
For map etc:
https://www.hs2.org.uk/work-items/notice-of-utility-investigations-near-west-ruislip-train-station/
from HS2
We have been informed that the London Borough of Hillingdon will have a full road closure at Breakspear Road South on Monday 14 June 2021, for one week to carry out resurfacing works from the south of the Chiltern Line bridge to Swakeleys junction.
As a result of these works, the SCS site team at Breakspear Road South have cancelled their works planned for next week. (Notice of works for the U46 footpath road crossing HS2-EW-SCS-Ph1-Ar-So-S1-Traf-33-14/06/2021)
from HS2
Newyears Green Lane
We wrote to you recently to advise you that we would be carrying out ecological surveys on 17 May and 1 June along Newyears Green Lane. Due to poor weather conditions, we were unable to complete the surveys. We therefore require additional time to complete these works, which will now be completed on 1 and 14 June 2021. A road closure will be required between 8pm and 5am to ensure these works can be carried out safely.
West Ruislip
We will be carrying out works over one weekend (19 & 20 June 2021) in the bell mouth where vehicles access the site from Ickenham High Road. We are connecting a foul sewer from site to a chamber that sits underneath the centre of the junction.
Once connected the trench will be backfilled and the work area reinstated. We will carry out the main cut into the concrete within normal working hours on the Friday 18 June, to minimise noise on the weekend
Duration of works
The weekend of 19 and 20 June 2021
From 8am to 6pm
What to expect
An excavator and dumper trucks will be required to create the trench for the sewer
What we will do
Maintain access along the footpath and carriageway of Ickenham High Road
We welcome Hillingdon Council’s 10 May announcement that it has sought a Judicial Review of the Mayor of London’s decision to grant permission for the most recent Master Brewer planning application.
We have repeatedly raised concerns about the way the Mayor has considered London Plan tall buildings policies, so we are pleased to see that this issue forms part of Hillingdon Council’s case.
As we set out earlier this year, the Mayor’s decision to grant permission was enormously disappointing for local community groups, who had invested time and effort in creating a community masterplan to show the sort of development that would be appropriate for the vacant site.
A Judicial Review is a type of court proceeding that considers the way in which a decision has been made, rather than the rights and wrongs of the conclusion reached. Over the next few weeks, a Judge will decide whether the case should be heard. If the case is heard and the Judge agrees with Hillingdon Council’s arguments, the Mayor could be ordered to reconsider the application.
From LBH
LONDON BOROUGH OF HILLINGDON TEMPORARY RESTRICTION OF TRAFFIC (BREAKSPEAR ROAD SOUTH, ICKENHAM) ORDER 2021 ROAD TRAFFIC REGULATION ACT 1984 SECTION 14(1)
1. Hillingdon Council gives notice that to enable repair works to be carried out by O’Hara Bros and to prevent the likelihood of danger to the public it made this Order, which will temporarily close Breakspear Road South, Ickenham from Swakeleys Road to outside Breakspear Road.
2. Diversion route will be in place via Breakspear Road, Bury Street, High Street, Ickenham Road, High Road, Swakeleys Road and vice versa. Nothing in the Order shall apply to prevent vehicular access to premises on or adjacent to the prohibited length of road insofar as access is reasonably practicable without interference with the said works.
3. The temporary restriction will be in operation between 08:00hrs on the 15 th June 2021 to 17:00hrs, on the 20th June 2021 and to such extent as indicated by traffic signs prescribed by the Traffic Signs Regulations and General Directions 2002. Road users should assume that the closure has been put into effect only if traffic signs have been erected stating that the road has been closed and the diversion route, if necessary is in place.
4. The Order, which is proposed will come into operation on 15 th June 2021, will continue in force for eighteen months or until work to which it relates is completed. However it is anticipated that the works will be completed within 5 Days.
Dated this 18 day of May 2021 Perry Scott Corporate Director of Infrastructure, Building Services & Transport
FROM HS2
Update:
We wrote to you in April to advise that we would be carrying out utility works from 17 May to 30 September 2021 and over two weekends. However, additional weekend working will be required.
From 17 May 2021, we will be carrying out utility surveys and utility connection along Harvil Road as part of the road realignment works. Temporary traffic management and lane closures will be required to ensure these works can be carried out safely.
We hope to reduce the duration of the lane closure by working additional weekends.