Ruislip Golf Course hoardings

From HS2:

Update: Activity along the border

Work is continuing to place secure wooden hoarding along the Network Rail border to the south of our work site and then extend it along the southernmost edge of our works. The hoarding will ensure that the work site is both safe and secure. Preparatory works are still taking place during the day, and work on Network Rail land is only taking place at night when trains are not running. This activity is taking longer than expected due to unexpectedly limited number of working hours available next to the railway.

All lights needed for work activity will be placed so that they face away from the residential properties.

The side of the hoarding facing the properties in The Greenway and Hoylake Crescent will be painted dark blue. This colour has been agreed with Network Rail who need to ensure that the red, amber, and green lights are visible to their drivers’ sight lines. here will be a period where e will remove the part of the cutting. This will be done during the day.

Duration of works These works will continue until 18 September at the latest Working hours Day time activity will be between 8am and 6pm Night time activity will happen between 12.30am and 7.45am on Sundays and 5.30am all other mornings, when no trains are running We may be on site for up to an hour before and after these hours for preparation This work is progressing east to west. What to expect An excavator to remove the hoarding post foundations. All other activity will be using hand tools.

LBH wins appeal against HS2 arrogance

Friday 31 July: Hillingdon Council has successfully persuaded the Court of Appeal to overturn a High Court decision concerning the submission of planning applications by HS2 Ltd under the HS2 Act.

The council had refused to approve an application for HS2 works to be undertaken on a site in the borough of archaeological importance on the basis that HS2 Ltd had submitted insufficient information in support of it.

HS2 Ltd disagreed with the council’s refusal decision and challenged it, by appealing to the government, on the basis that it was not required to provide the information which the council required as it could instead rely upon a suite of non-statutory documents, known as Environmental Minimum Requirements, which would provide the council with the necessary assurances that the archaeological integrity of the site would be maintained and that HS2 Ltd would, if necessary, carry out its own future investigations as a means of safeguarding it.

The council sought a judicial review of the government’s decision to allow HS2 Ltd’s appeal but in December 2019, the High Court found in the government’s favour.

The Court of Appeal handed down its judgement today. It ruled that HS2 Ltd cannot rely upon the Environmental Requirements and that it has to provide sufficient information to the council in support of its planning applications. The council is under no obligation to determine the applications unless and until it receives such information. The Court of Appeal also frowned upon HS2 Ltd’s contention that it is permissible for it to carry out its own investigations, as part of the application process, saying that it would not have been the intention of Parliament to ‘set up a scheme which gave the appearance that HS2 Ltd was a judge in its own cause’. The government has also been ordered to pay the council’s legal costs of both the High Court and Court of Appeal cases.

Councillor Ray Puddifoot, Leader of Hillingdon Council, said: ”HS2 Ltd thought that HS2 could act with total impunity and just expect the Council to approve its planning applications without question. As the Court of Appeal has said, it cannot have been the intention of Parliament to allow HS2 Ltd to be a judge in its own cause. For the avoidance of doubt, this council will continue to challenge decisions that may harm our environment or the health and wellbeing of our people.”

https://hillingdon.gov.uk/article/5397/Hillingdon-Council-wins-HS2-planning-case-in-Court-of-Appeal

Copthall Road East works

From LBH:

As part of this year’s planned carriageway resurfacing programme, work is due to be carried out on  Copthall Road East  from the week commencing  27 July 2020. 

 

We will place advance Notices on the streets giving the actual start date.

The hours of working will be 8.00 am to 5.00 pm, (Monday to Saturday).

The start date and duration period may be subject to change due to prevailing weather conditions or unforeseen issues.