Full description of upcoming A40 closures – between Swakeleys and Denham roundabouts.
HS2 works at Harvil Road 01-07-2021 to 31-03-2022
from HS2
Estimated Start Date
01/07/2021
Estimated End Date
31/03/2022
Work item details
What we are doing
Over the coming months we will be carrying out enabling works in the Harvil Road area. These works will allow us to prepare the area which is required for the temporary storage and treatment of the soil that will be removed from the tunnels, before they are placed in their final location.
Our initial works will include:
- Setting up security fencing and hoarding
- Delivery of equipment for the removal of topsoil
- Vegetation clearance, including brambles and hedgerows
- Preparation works to secure and divert a section of the U49 footpath around the works area
More info and map:
https://www.hs2.org.uk/work-items/notice-of-preparation-works-for-the-soil-treatment-area-at-harvil-road/
Planning updates 06-07-2021
This week’s planning decisions, applications and appeals. Click on the link or download the pdf. The pdf gives you direct links to the LBH planning and appeal search pages.
Latest Ickenham Residents’ Association Newsletter
This from the IRA:
At long last we are able to print and deliver our latest newsletter
They should be with your road stewards early this week and with you shortly afterwards
We hope all our members get one dropping through their letterbox but just in case we will be leaving copies in the Library and, hopefully, in Maison du Soleil
This edition will NOT be available on our website.
We will not be collecting subs at the this time but hope to do so later in the year.
Thank you to our delivery team for their help and support
U46 Footpath Diversion
| from HS2 The U46 footpath diversion We are progressing to a stage in our works where we will be diverting a number of footpaths. These works will facilitate the completion of the internal haul road and help to keep as many vehicles off local roads as possible. Our first diversion is the U46 footpath, the short footpath that runs from the Celandine Way to Breakspear Road South near Oak Farm. The surface of U43 has been improved and extended and it currently progresses south behind the trees and emerges at a marked crossing point in Breakspear Road South. Please see map on link below. https://www.hs2.org.uk/work-items/notice-of-the-u46-footpath-diversion/ |
September URC Jumble Sale
From URC:
|
Planning updates 28-06-2021
This week’s planning decisions, applications and appeals (if any). Click on the link or download the pdf. The pdf gives you direct links to the LBH planning and appeal search pages.
HS2 surveys at Breakspear Road South (12-16 July) and Harvil Road (26-30 July)
From HS2
From 12 to 30 July 2021, we will be carrying out overnight surveys along Breakspear Road South and Harvil Road. This will help to inform our design decisions in the area.
Survey duration
• Breakspear Road South from 12 to 16 July
• Harvil Road from 26 to 30 July
Your utility services will not be affected.
Northolt training flights evening of 24 June 2021
From the MoD:
32 (TR) Sqn will be conducting routine night currency training using BAe 146 aircraft up to 2300L on the evening of 24 June 2021. This will involve a number of approaches to the runway, outside of the station’s usual/published operating hours.
[ I think the L must mean Local time ]
HS2 plans extended working hours
From HS2
Works are ongoing at our sites at Harvil Road and Newyears Green Lane to build the new road realignment, the Copthall Tunnels and the conveyor system. Some of these works will need to take place during extended working hours.
From 7 July until 31 October 2021, we will be extending our working hours on our sites and will be undertaking work on site from 7am to 6pm, Monday through Saturday. This is an extension of our core working hours of 8am to 6pm Monday to Friday and 8pm to 1pm on Saturdays.